Current through Register Vol. 50, No. 9, September 20, 2024
A. Disinfection may
be accomplished with gas and liquid chlorine, calcium or sodium hypochlorites,
chlorine dioxide, chloramines, ozone, or ultraviolet light. Other disinfecting
agents will be considered, providing reliable application equipment is
available and testing procedures for a residual are recognized in "Standard
Methods for the Examination of Water and Wastewater,". Disinfection is required
for all water systems in accordance with
§355 and
§357 of this Part, other than those
public water systems holding valid disinfection variance in accordance with
§361 of this Part.
B. Chlorination. Design criteria for
chlorination shall be as follows.
1.
Chlorination Equipment Type. Solution-feed gas chlorinators or hypochlorite
feeders of the positive displacement type shall be provided. (see §201-209
"Chemical Application" of this Part).
2. Capacity. The chlorinator capacity shall
be sufficient to comply with minimum chlorine residuals required in
§355 and
§357 of this Part. The equipment shall be
of such design that it will operate accurately over the desired feeding
range.
3. Standby Equipment.
Standby equipment shall be available to replace/repair a critical unit unless
an alternative is approved by the state health officer. Spare parts shall be
readily available to replace parts subject to wear and breakage. If there is a
large difference in feed rates between routine and emergency dosages, a gas
metering tube should be provided for each dose range to ensure accurate control
of the chlorine feed.
4. Automatic
Switch-Over. Automatic switch-over of chlorine cylinders shall be provided to
assure continuous disinfection.
5.
Eductor. Each eductor shall be selected for the point of application with
particular attention given to the quantity of chlorine to be added, the maximum
injector water flow, the total discharge back pressure, the injector operating
pressure, and the size of the chlorine solution line. Gauges for measuring
water pressure and vacuum at the inlet and outlet of each eductor should be
provided.
6. Injector/Diffuser. The
chlorine solution injector/diffuser shall be compatible with the point of
application to provide a rapid and thorough mix with all the water being
treated.
C. Criteria for
Contact Time and Point of Application
1. Due
consideration shall be given to the contact time of the disinfectant in water
with relation to pH, ammonia, taste-producing substances, temperature,
bacterial quality, disinfection byproduct formation potential and other
applicable factors. The disinfectant should be applied at a point which will
provide adequate contact time (CT). All basins used for disinfection shall be
designed to minimize short circuiting.
2. For treating surface waters and
groundwaters under the direct influence of surface water, the system shall be
designed to meet the CT standards set in Chapter 11 of this Part.
D. Residual Chlorine. Systems
shall be designed to meet the minimum disinfectant residual per
§355 and
§357 of this Part.
E. Testing Equipment. Testing equipment used
for compliance monitoring shall comply with approved analytical methods set
forth in this Part.
F. Chlorinator
Piping. Design criteria for chlorinator pipping shall be as follows.
1. Cross-Connection Protection. The
chlorinator water supply piping shall be designed to prevent contamination of
the treated water supply in accordance with the backflow prevention
requirements set forth in
§344 of this Part.
2. Pipe Material. The pipes carrying
elemental liquid or dry gaseous chlorine under pressure shall be Schedule 80
seamless steel tubing or other materials recommended by the Chlorine Institute.
PVC is not acceptable upstream of the vacuum regulator. Vacuum piping for
gaseous chlorine shall be polyethylene tubing or Schedule 80 PVC pipe. Rubber,
Schedule 80 PVC, or polyethylene shall be used for chlorine solution piping and
fittings.
G.
Chloramination. Chloramination is an application of ammonia and chlorine at a
proper mass ratio of chlorine to ammonia to produce a combined chlorine
residual predominantly in form of monochloramine. Proper chlorine to ammonia
ratio shall be maintained to prevent the formation of dichloramine and
trichloramine which create taste and odor in drinking water.
1. Type. The chlorine system shall comply
with the applicable requirements of §179.B Ammonia systems shall supply either
anhydrous ammonia, ammonium sulfate or aqua ammonia in compliance with the
requirements of §§201-209 "Chemical Application" of this Part.
2. Capacity. The ammonia supply system shall
have sufficient capacity to comply with minimum disinfectant residuals required
in
§355 and
§357 of this Part. The equipment shall be
of such design that it will operate accurately over the desired feeding
range.
3. Standby Equipment.
Standby equipment shall be available to replace/repair a critical unit. Spare
parts shall be made available to replace parts subject to wear and
breakage.
4. Injector/Diffuser. The
ammonia injector/diffuser shall be compatible with the point of application to
provide a rapid and thorough mix with all the water being treated. If injectors
are used, provisions for scale formation shall be considered.
a. Ammonia solution shall be fed through
injectors/diffusers made of appropriate material installed per manufacturers
recommendations for even distribution of the solution. Materials containing
copper shall not be used in contact with the ammonia.
5. Cross-Connection Protection. The aqua
ammonia water supply piping shall be designed to prevent contamination of the
treated water supply in accordance with the backflow prevention requirements
set forth in
§346 of this Part.
6. Pipe Material. The pipes carrying
anhydrous ammonia shall be black iron or stainless steel. Aqua (Aqueous)
ammonia or ammonium sulfate piping shall be stainless steel, polyethylene
tubing or schedule 80 PVC. Stainless steel, rubber, polyethylene tubing or PVC
shall be used for aqueous ammonia solution piping and fittings.
H. Ozone
1. Design considerations include the
following.
a. Ozonation systems are generally
used for the purpose of disinfection, oxidation and
microflocculation.
b. Bench scale
studies shall be conducted to determine minimum and maximum ozone dosages for
disinfection "CT" compliance and oxidation reactions. More involved pilot
studies shall be conducted when necessary to document benefits and DBP
precursor removal effectiveness. Consideration shall be given to multiple
points of ozone addition. Pilot studies shall be conducted for all surface
waters. Particularly sensitive measurements include gas flow rate, water flow
rate, and ozone concentration.
c.
Following the use of ozone, the application of a disinfectant which maintains a
measurable residual will be required in order to ensure bacteriologically safe
water is carried throughout the distribution system.
d. Furthermore, because of the more
sophisticated nature of the ozone process a higher degree of operator
maintenance skills and training is required. The ability to obtain qualified
operators must be evaluated in selection of the treatment process. The
necessary operator training shall be provided prior to plant startup. An
operation and maintenance manual shall be provided and maintained onsite while
the ozone unit is in operation.
2. Feed Gas Preparation. General design
criteria for feed gas preparation shall be as follows.
a. Feed gas can be air, oxygen enriched air,
or high purity oxygen. Sources of high purity oxygen include purchased liquid
oxygen; on site generation using cryogenic air separation; or temperature,
pressure or vacuum swing (adsorptive separation) technology. For high purity
oxygen-feed systems, dryers typically are not required.
i. Air handling equipment on conventional low
pressure air feed systems shall consist of an air compressor, water/air
separator, refrigerant dryer, heat reactivated desiccant dryer, and particulate
filters. Some "package" ozonation systems for small plants may work effectively
operating at high pressure without the refrigerant dryer and with a "heat-less"
desiccant dryer. The maximum dew point of -76°F (-60°C) will not be exceeded at
any time.
b. Air
compression. Design criteria for air compression shall be as follows.
i. Air compressors shall be of the
liquid-ring or rotary lobe, oil-less, positive displacement type for smaller
systems or dry rotary screw compressors for larger systems.
ii. The air compressors shall have the
capacity to simultaneously provide for maximum ozone demand, provide the air
flow required for purging the desiccant dryers (where required) and allow for
standby capacity.
iii. Air feed for
the compressor shall be drawn from a point protected from rain, condensation,
mist, fog and contaminated air sources to minimize moisture and hydrocarbon
content of the air supply.
iv. A
compressed air after-cooler and/or entrainment separator with automatic drain
shall be provided prior to the dryers to reduce the water vapor.
v. A back-up air compressor must be provided
so that ozone generation is not interrupted in the event of a
break-down.
c. Air
drying. Design criteria for air drying shall be as follows.
i. Dry, dust-free and oil-free feed gas must
be provided to the ozone generator. Dry gas is essential to prevent formation
of nitric acid, to increase the efficiency of ozone generation and to prevent
damage to the generator dielectrics. Sufficient drying to a maximum dew point
of -76°F (-60°C) shall be provided at the end of the drying cycle.
ii. Drying for high pressure systems may be
accomplished using heatless desiccant dryers only. For low pressure systems, a
refrigeration air dryer in series with heat-reactivated desiccant dryers shall
be used.
iii. A refrigeration dryer
capable of reducing inlet air temperature to 40°F (4°C) shall be provided for
low pressure air preparation systems.
iv. For heat-reactivated desiccant dryers,
the unit shall contain two desiccant filled towers complete with pressure
relief valves, two four-way valves and a heater. External type dryers shall
have a cooler unit and blowers. The size of the unit shall be such that the
specified dew point will be achieved during a minimum adsorption cycle time of
16 hours while operating at the maximum expected moisture loading
conditions.
v. Multiple air dryers
shall be provided so that the ozone generation is not interrupted in the event
of dryer breakdown.
vi. Each dryer
shall be capable of venting "dry" gas to the atmosphere, prior to the ozone
generator, to allow start-up when other dryers are
"on-line".
d. Air
filters. Design criteria for air filters shall be as follows.
i. Air filters shall be provided on the
suction side of the air compressors, between the air compressors and the dryers
and between the dryers and the ozone generators.
ii. The filter before the desiccant dryers
shall be of the coalescing type and be capable of removing aerosol and
particulates larger than 0.3 microns in diameter. The filter after the
desiccant dryer shall be of the particulate type and be capable of removing all
particulates greater than 0.1 microns in diameter, or smaller if specified by
the generator manufacturer.
e. Preparation piping. Piping in the air
preparation system can be common grade steel, seamless copper, stainless steel
or galvanized steel. The piping must be designed to withstand the maximum
pressures in the air preparation system.
3. Ozone Generator. Design criteria for ozone
generators shall be as follows.
a. Capacity.
Design criteria for ozone generator capacity shall be as follows.
i. The production rating of the ozone
generators shall be stated in pounds per day and kWhr per pound at a maximum
cooling water temperature and maximum ozone concentration.
ii. The design shall ensure that the minimum
concentration of ozone in the generator exit gas will not be less than 1
percent (by weight).
iii.
Generators shall be sized to have sufficient reserve capacity so that the
system does not operate at peak capacity for extended periods of
time.
iv. The production rate of
ozone generators will decrease as the temperature of the coolant increases. If
there is to be a variation in the supply temperature of the coolant throughout
the year, then applicable data shall be used to determine production changes
due to the temperature change of the supplied coolant. The design shall ensure
that the generators can produce the required ozone at maximum coolant
temperature.
v. Appropriate ozone
generator backup equipment must be provided.
b. Electrical. The generators can be low,
medium or high frequency type. Specifications shall require that the
transformers, electronic circuitry and other electrical hardware be proven,
high quality components designed for ozone service.
c. Cooling. Adequate cooling shall be
provided. The cooling water must be properly treated to minimize corrosion,
scaling and microbiological fouling of the water side of the tubes. Where
cooling water is treated, cross connection control shall be provided to prevent
contamination of the potable water supply in accordance with the backflow
prevention requirements in
§344 of this Part.
d. Materials. The ozone generator shell and
tubes shall be constructed of Type 316L stainless steel.
4. Ozone Contactors. The selection or design
of the contactor and method of ozone application depends on the purpose for
which the ozone is being used.
a. Bubble
Diffusers. Design criteria for bubble diffusers shall be as follows.
i. Where disinfection is the primary
application a minimum of two contact chambers each equipped with baffles to
prevent short circuiting and induce counter current flow shall be provided.
Ozone shall be applied using porous-tube or dome diffusers.
ii. The minimum contact time shall be 10
minutes. A shorter contact time may be approved by state health
officer.
iii. The contactor must be
kept under negative pressure and sufficient ozone monitors shall be provided to
protect worker safety. The secondary enclosure for the ozone contactor shall be
open to the atmosphere.
iv. Large
contact vessels made of reinforced concrete shall comply with ACI 350. All
reinforcement bars shall be covered with a minimum of 2.0 inches of concrete.
Smaller contact vessels can be made of stainless steel, fiberglass or other
material which will be stable in the presence of residual ozone and ozone in
the gas phase above the water level.
v. Where necessary a system shall be provided
between the contactor and the off-gas destruct unit to remove froth from the
air and return the other to the contactor or other location acceptable to the
state health officer. If foaming is expected to be excessive, then a potable
water spray system shall be placed in the contactor head space.
vi. All openings into the contactor for pipe
connections, hatchways, etc. shall be properly sealed using welds or ozone
resistant gaskets such as Teflon or Hypalon.
vii. Multiple sampling ports shall be
provided to enable sampling of each compartment's effluent water and to confirm
"CT" calculations.
viii. A
pressure/vacuum relief valve shall be provided in the contactor and piped to a
location where there will be no damage to the destruction unit.
ix. The diffusion system shall work on a
countercurrent basis such that the ozone is fed at the bottom of the vessel and
water is fed at the top of the vessel.
x. The depth of water in bubble diffuser
contactors shall be a minimum of 18 feet. The contactor should also have a
minimum of 3 feet of freeboard to allow for foaming.
xi. All contactors shall have provisions for
cleaning, maintenance and drainage of the contactor. Each contactor compartment
shall also be equipped with an access hatchway.
xii. Aeration diffusers shall be fully
serviceable by either cleaning or replacement.
b. Other Contactors. Other contactors, such
as the venturi or aspirating turbine mixer contactor, may be approved by the
state health officer provided adequate ozone transfer is achieved and the
required contact times and residuals can be met and verified.
5. Ozone Destruction Unit. Design
criteria for ozone destruction unit shall be as follows.
a. A system for treating the final off-gas
from each contactor shall be provided in order to meet safety and air quality
standards. Acceptable systems include thermal destruction and thermal/catalytic
destruction units.
b. The maximum
allowable ozone concentration in the discharge is 0.1 ppm (by
volume).
c. At least two units
shall be provided which are each capable of handling the entire gas
flow.
d. Exhaust blowers shall be
provided in order to draw off-gas from the contactor into the destruct
unit.
e. Catalysts shall be
protected from froth, moisture and other impurities which may harm the
catalyst.
f. The catalyst and
heating elements shall be located where they can easily be reached for
maintenance.
6. Piping
Materials. Only low carbon 304L and 316L stainless steels shall be used for
ozone service.
7. Joints and
Connections. Design criteria for ozone joints and connections shall be as
follows.
a. Connections on piping used for
ozone service are to be welded where possible.
b. Connections with meters, valves or other
equipment are to be made with flanged joints with ozone resistant gaskets, such
as Teflon of Hypalon.
c. A positive
closing plug or butterfly valve plus a leak-proof check valve shall be provided
in the piping between the generator and the contactor to prevent moisture
reaching the generator.
8. Instrumentation. Design criteria for ozone
instrumentation shall be as follows.
a.
Pressure gauges shall be provided at the discharge from the air compressor, at
the inlet to the refrigeration dryers, at the inlet and outlet of the desiccant
dryers, at the inlet to the ozone generators and contactors and at the inlet to
the ozone destruction unit.
b.
Electric power meters shall be provided for measuring the electric power
supplied to the ozone generators. Each generator shall have a trip which shuts
down the generator when the wattage exceeds a certain preset level.
c. Dew point monitors shall be provided for
measuring the moisture of the feed gas from the desiccant dryers. Because it is
critical to maintain the specified dew point, it is recommended that continuous
recording charts be used for dew point monitoring which will allow for proper
adjustment of the dryer cycle. Where there is potential for moisture entering
the ozone generator from downstream of the unit or where moisture accumulation
can occur in the generator during shutdown, post-generator dew point monitors
shall be used.
d. Air flow meters
shall be provided for measuring air flow from the desiccant dryers to each of
other ozone generators, air flow to each contactor and purge air flow to the
desiccant dryers.
e. Temperature
gauges shall be provided for the inlet and outlet of the ozone cooling water
and the inlet and outlet of the ozone generator feed gas, and, if necessary,
for the inlet and outlet of the ozone power supply cooling water.
f. Water flow meters shall be installed to
monitor the flow of cooling water to the ozone generators and, if necessary, to
the ozone power supply.
g. Ozone
monitors shall be installed to measure zone concentration in both the feed-gas
and off-gas from the contactor and in the off-gas from the destruct unit. For
disinfection systems, monitors shall also be provided for monitoring ozone
residuals in the water. The number and location of ozone residual monitors
shall be such that the amount of time that the water is in contact with the
ozone residual can be determined.
h. A minimum of one ambient ozone monitor
shall be installed in the vicinity of the contactor and a minimum of one shall
be installed in the vicinity of the generator. Ozone monitors shall also be
installed in any areas where ozone gas may accumulate.
9. Alarms. The following alarm/shutdown
systems shall be considered at each installation:
a. dew point shutdown/alarm. This system
should shut down the generator in the event the system dew point exceeds -76°F
(-60°C);
b. ozone generator cooling
water flow shutdown/alarm. This system should shut down the generator in the
event that cooling water flows decrease to the point that generator damage
could occur;
c. ozone power supply
cooling water flow shutdown/alarm. This system should shut down the power
supply in the event that cooling water flow decreases to the point that damage
could occur to the power supply;
d.
ozone generator cooling water temperature shutdown/alarm. This system should
shutdown the generator if either the inlet or outlet cooling water exceeds a
certain preset temperature;
e.
ozone power supply cooling water temperature shutdown/alarm. This system should
shutdown the power supply if either the inlet or outlet cooling water exceeds a
certain preset temperature;
f.
ozone generator inlet feed-gas temperature shutdown/alarm. This system should
shutdown the generator if the feed-gas temperature is above a preset
value;
g. ambient ozone
concentration shutdown/alarm. The alarm should sound when the ozone level in
the ambient air exceeds 0.1 ppm or a lower value chosen by the water supplier.
Ozone generator shutdown should occur when ambient ozone levels exceed 0.3 ppm
(or a lower value) in either the vicinity of the ozone generator or the
contactor; and
h. ozone destruct
temperature alarm. The alarm should sound when temperature exceeds a preset
value.
10. Safety.
Design criteria for ozone safety shall be as follows.
a. The maximum allowable ozone concentration
in the air to which workers may be exposed must not exceed 0.1 ppm (by
volume).
b. Emergency exhaust fans
shall be provided in the rooms containing the ozone generators to remove ozone
gas if leakage occurs.
c. A sign
shall be posted indicating "No smoking, oxygen in use" at all entrances to the
treatment plant. In addition, no flammable or combustible materials shall be
stored within the oxygen generator areas.
I. Chlorine Dioxide. When choosing chlorine
dioxide, consideration must be given to formation of the regulated byproducts
and chlorite.
1. Chlorine Dioxide Generators.
Chlorine dioxide generation equipment shall be factory assembled pre-engineered
units with a minimum efficiency of 95 percent. The excess free chlorine shall
not exceed five percent of the theoretical stoichiometric concentration
required. Generators designed or intended to operate outside of this criteria
shall require justification and be considered on a case-by-case basis.
Generator yield shall be defined as the ratio of chlorine dioxide generated to
the theoretical stoichiometric maximum, as presented in EPAs Alternative
Disinfectants and Oxidants Guidance Manual, Section 4.2 2 (EPA 815-R-99-014,
April 1999).
a. Generators shall be designed,
built and certified in compliance to NSF 61.
b. Bench scale testing shall be conducted to
determine chlorine dioxide demand and decay kinetics for the specific water
being treated in order to establish the correct design dose for required log
inactivation compliance (if required), oxidation reactions, and chlorite
generation.
c. An operation and
maintenance manual (O&M) shall be provided. The O&M shall cover, at a
minimum, operating instructions, identification and location of components,
maintenance information and checklists; manufacturers product information
(including trouble shooting information, a parts list and parts order form,
special tools, spare parts list, etc.) and a chlorine dioxide and chlorite
residual monitoring action plan (RMAP). The RMAP shall identify actions to be
taken by properly trained certified operators in the event that the chlorine
dioxide residual or chlorite level meet or exceed specified maximum levels at
specified testing locations (e.g., generator effluent, treatment units,
point-of-entry).
d. Certified
operators charged with handling and/or conducting chlorine dioxide and chlorite
testing shall be properly trained on the production and testing equipment, the
generator O&M manual, and the RMAP. Documentation of training shall be
signed by the individual having responsible authority over the operators.
Training documentation shall be provided to the OPH District Office and
maintained on-site for review during sanitary surveys.
2. Feed and storage facilities. When chlorine
gas and sodium chlorite are used feed and storage facilities shall comply with
§209. A and §209. C of this Part, respectively. Sodium hypochlorite feed and
storage facilities shall comply with §209. D of this Part. All chlorine dioxide
feed and storage facilities shall comply with §179. 1.5 and §179.1 6 of this
Part.
3. Other design requirements
shall include the following.
a. The design
shall comply with all applicable portions of §179 B, §179 C, and §179. F of
this Part.
b. Alarms shall be
provided to indicate a lack of chemical (chlorine and sodium chlorite) or
motive water flow.
4.
Public Notification. Notification of a change in disinfection practices and the
schedule for the changes shall be made known to the public; particularly to
hospitals, kidney dialysis facilities, and fish breeders, as chlorine dioxide
and its byproducts may have similar effects as chloramines.
5. Chlorine Dioxide Feed System. Design
criteria for chlorine dioxide feed system shall be as follows.
a. Use fiberglass reinforced vinyl ester
plastic (FRP) or high density linear polyethylene (HDLPE) tanks with no
insulation.
b. If centrifugal pumps
are used, provide Teflon packing material. Pump motors must be totally
enclosed, fan-cooled, equipped with permanently sealed bearings, and equipped
with double mechanical seals or other means to prevent leakage.
c. Provide chlorinated PVC, vinyl ester or
Teflon piping material. Do not use carbon steel or stainless steel piping
systems.
d. Provide glass view
ports for the reactor if it is not made of transparent material.
e. All chlorite solutions shall have
concentrations less than 30 percent. Higher strength solutions are susceptible
to crystallization and stratification.
6. Chlorine Dioxide Storage Requirements.
Design criteria for chlorine dioxide storage shall be as follows.
a. Chlorine dioxide storage and operating
area shall conform to the following.
i. The
chlorine dioxide facility shall be physically located in a separate room from
other water treatment plant operating areas.
ii. The chlorine dioxide area shall have a
ventilation system separate from other operating areas.
iii. Provision shall be made to ventilate the
chlorine dioxide facility area and maintain the ambient air chlorine dioxide
concentrations below the Permissible Exposure Limit (PEL).
(a). The ventilating fan(s) take suction near
the floor, as far as practical from the door and air inlet, with the point of
discharge so located as not to contaminate air inlets of any rooms or
structures.
(b). Air inlets are
provided near the ceiling.
(c). Air
inlets and outlets shall be louvered.
(d). Separate switches for the fans are
outside and near the entrance of the facility.
iv. There shall be observation windows
through which the operating area can be observed from outside the room to
ensure operator safety.
v. Manual
switches to the light in the operating area shall be located outside the door
to the room.
vi. An emergency
shutoff control to shut flows to the generator shall be located outside the
operating area.
vii. Gaseous
chlorine feed to the chlorine dioxide generator shall enter the chlorine
dioxide facility area through lines which can only feed to vacuum.
viii. There shall not be any open drains in
the chlorine dioxide operating area.
J. Ultraviolet Light. Any Ultraviolet unit
installed for treatment of cryptosporidium is required to meet the requirements
of the USEPAs 2006 Ultraviolet Disinfection Guidance Manual.
K. Other disinfecting agents. Use of
disinfecting agents other than those listed shall be approved by the state
health officer prior to preparation of final plans and
specifications.
AUTHORITY NOTE:
Promulgated in accordance with the provisions of
R.S.
40:4.A.(8), 40:4.13.D.(1)(2) and
40:5.A.(2)(3)(5)(6)(7)(17).