A. Immediately following completion of all aerial triangulation work or sub-block portions thereof, the contractor shall prepare a formal aerial triangulation report for submission to and approval by the responsible contracting authority. This report will include but not necessarily be limited to the following.
1.
Photo index overlays:
a. flight line and
exposure stations;
b. all control
points and checkpoints used, appropriately labeled with station designations,
computer designations (if different), agency responsible for establishing the
stations, orders of accuracy, and an indication of whether individual points
were targeted or photo identifiable;
c. all misclosures (DX, DY, DZ) at ground
control and check points appropriately labeled with station
designations;
d. note that overlays
§1121. A.1 a, b, and
c above may be combined all onto one single overlay at the contractor's option
if the resultant product is clear and legible. Misclosures in DX and DY may be
symbolized as vectors to some appropriate scale if the contractor so
chooses.
2.
Aerotriangulation results:
a. tabulation of
all misclosures at ground control points used in the solution;
b. computed coordinates of all control
points, passpoints and checkpoints;
c. computed coordinates of all resected
camera stations with their orientations;
d. comparator coordinates of all points
measured (including fiducials) sorted or arranged by individual frame.
Plate-centered coordinates may be substituted for comparator coordinates if the
contractor so chooses;
e. post
adjustment plate residuals of all image coordinates used in the
solution;
f. coordinates of LSR
origin used for solution;
g.
comparator calibration coefficients if comparator coordinates are furnished
instead of plate-centered coordinates;
h. variance-covariance matrices of all
triangulated positions and altitudes if an error propagation analysis was
performed on the adjustment solution.
3. Narrative. The report shall include a
brief narrative trying together
§1121. A.1 and 2, and
including descriptions of laboratory equipment, procedures and computer
programs used. If comparator coordinates are furnished by the contractor, the
comparator calibration correction equations shall be documented in the
narrative to allow the responsible contracting authority to evaluate the
coefficients supplied as well as to compute plate coordinates. Root-Mean-Square
(rms) error summaries will be given for bundle adjustment residuals of all
control points. Furthermore, misfits encountered at control points that
required corrective action shall be clearly described along with descriptions
of corrective actions taken.
B.Section 1121. A.2 a-h shall be submitted on acceptable PC-DOS or MS-DOS formatted computer transfer media in ASCII file format subject to the discretion and approval of the responsible contracting authority.
AUTHORITY NOTE: Promulgated in accordance with R.S. 50:171.
Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.