Louisiana Administrative Code
Title 43 - NATURAL RESOURCES
Part XVII - Office of Conservation-Injection and Mining
Subpart 7 - Statewide Order No. 29-M-5
Chapter 37 - Storage Wells in Solution-Mined Salt Dome Cavities
Section XVII-3723 - Monitoring Requirements
Current through Register Vol. 50, No. 9, September 20, 2024
A. Pressure Gauges, Pressure Sensors, Flow Sensors
B. Continuous Recording Instruments. Continuous recording instrumentation shall be installed and properly maintained for each storage well. Continuous recordings may consist of circular charts, digital recordings, or similar type. Unless otherwise specified by the commissioner, digital instruments shall record the required information at no greater than one minute intervals. Mechanical charts shall not exceed a clock period of 24-hour duration. The chart shall be selected such that its scaling is of sufficient sensitivity to record all fluctuations of pressure or any other parameter being monitored. The chart shall be scaled such that the parameter being recorded is 30 percent to 70 percent of full scale. Instruments shall be housed in weatherproof enclosures when located in areas exposed to climatic conditions. All fluid volumes shall be determined by metering or an alternate method approved by the Office of Conservation. Minimum data recorded shall include the following:
C. Casing Inspection
D. Vapor Detection. Unless specifically exempted by the commissioner, the operator shall develop a robust monitoring plan designed to detect the presence of a buildup of combustible gases or any potentially ignitable substances in the atmosphere resulting from the Class V storage operation. Variations in surface topography, atmospheric conditions typical to the area, characteristics of the stored product, proximity of the facility to homes, schools, commercial establishments, other wells or injection wells, etc., should be considered in developing the monitoring plan. The plan shall be submitted as part of the permit application and updated as needed but no less than every five years, and may be included within the submittal required in §3709.K The monitoring plan should include provisions for strategic placement of stationary detection devices at various areas of the facility, portable monitoring devices, downhole monitoring devices, or any other appropriate system acceptable to the commissioner.
E. Subsidence Monitoring and Frequency. The owner or operator shall prepare and carry out a plan approved by the commissioner to monitor ground subsidence at and in the vicinity of the storage cavern(s). A monitoring report shall be prepared and submitted to the Office of Conservation after completion of each monitoring event.
F. Wind Sock. At least one windsock shall be installed at all storage cavern facilities. The windsock shall be visible from any normal work location within the facility.
G. Monitor Wells. Quarterly monitoring of any monitor wells required by §3717.A.2.a
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4 et seq. and R.S. 30:23 et seq.