Section XV-5393 - Coal Processing Waste: Dams and Embankments-Site Preparation
Universal Citation: LA Admin Code XV-5393
Current through Register Vol. 50, No. 9, September 20, 2024
A. Before coal processing waste is placed at a dam or embankment site:
1. All trees, shrubs, grasses and other
organic material shall be cleared and grubbed from the site, and all
combustibles shall be removed and stockpiled in accordance with the
requirements of this Chapter.
2.
Surface drainage that may cause erosion to the embankment area or the
embankment features, whether during construction or after completion, shall be
diverted away from the embankment by diversion ditches that comply with the
requirements of
§5323 Adequate outlets for discharge from
these diversions shall be in accordance with
§5329 Diversions that are designed to
divert drainage from the upstream area away from the impoundment area shall be
designed to carry the peak runoff from a 100-year, 6-hour precipitation event.
The diversion shall be maintained to prevent blockage, and the discharge shall
be in accordance with
§5329 Sediment control measures shall be
provided at the discharge of each diversion ditch before entry into natural
watercourses in accordance with §5319-5327
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:901-932.
Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.