A. On and after the effective date hereof, a permit to multiply complete a new or existing well in separate pools, where the proposed completions are in compliance with all applicable Office of Conservation statewide orders, may be obtained by submitting a complete application to drill, as outlined in Part XIX, Subpart 1 (Statewide Order No. 29-B), for each proposed completion concurrent with drilling and/or workover operations on the first completion, or at such other time as a desire to make a multiple completion is known, together with the prescribed fees in accordance with the procedure hereinafter outlined.
B. In the instance where a multiple completion is applied for, the completions must be in separate pools and the following procedure will be followed in submitting the required data for each multiple completion.
C. An allowable will be granted for each completion of a multiply completed well upon the filing of all information, as prescribed in §1305. B.2 above, and after a permit to drill has been issued for each pool in which a completion has been made.
D. In the event the Commissioner of Conservation approves the multiple completion as requested, the following shall be complied with.
E. Should the zones approved for multiple completion become intercommunicative, the operator shall immediately repair and separate the pools.
F. Each separate completion shall be considered a separate well as to permits, allowables, fees and for all other purposes.
G. The use of selective completion equipment in separate pools is expressly prohibited except as provided herein and no work should precede approval by the Commissioner of Conservation of the application which shall be filed in duplicate with the appropriate district manager.
H. Notwithstanding the provisions of the previous Paragraph, an application for selective completion may be filed with the appropriate district manager for a well that does not meet all requirements set forth in §1305. G upon showing for good cause that such request should be considered. An exceptional application of this nature will be considered for administrative approval by the Commissioner of Conservation upon recommendation of the district manager as a last resort to prevent the loss of oil and gas that could not be recovered by any other means than through the use of selective completion equipment or under other exceptional circumstances as determined to be appropriate by the commissioner.
I. In the event a well is authorized for selective completion in separate pools, the operator thereof shall continuously monitor the performance of such well in an effort to determine that the separate pools remain isolated and shall secure a work permit from the district manger before affecting a change from one separate pool to another through the use of the downhole selective equipment. Also, each such change in pool shall be considered a recompletion and all reports normally filed when recompleting a well will be required.
J. The foregoing shall supersede and replace the provisions of Statewide Order No. 29-C, and all prior amendments thereto and all prior memoranda issued thereunder and shall govern the multiple and selective completion of wells productive of hydrocarbons in the state of Louisiana.
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4 et seq.