Louisiana Administrative Code
Title 43 - NATURAL RESOURCES
Part XIX - Office of Conservation-General Operations
Subpart 1 - Statewide Order No. 29-B
Chapter 5 - Off-Site Storage, Treatment and/or Disposal of Exploration and Production Waste Generated from Drilling and Production of Oil and Gas Wells
Section XIX-571 - Requirements for E and P Waste Transfer Pipeline Systems
Universal Citation: LA Admin Code XIX-571
Current through Register Vol. 50, No. 9, September 20, 2024
A. Notification
1. The Office of Conservation shall be
notified in writing at least 30 days prior to installation of an offsite E and
P waste transfer pipeline system. Written notification shall include the
following items:
a. the pipeline system
operator/company name, address and principal officer contact information
including emergency contacts;
b.
estimated timeframe construction will begin;
c. a list of all E and P waste types to be
transported via the pipeline system;
d. a list of all E and P waste
operators/generators that will utilize the pipeline system;
e. a narrative description, map(s) and
schematic diagram(s) as necessary to accurately describe the geographic
location of the entire pipeline system to be operated in Louisiana, the
pipeline system starting and ending point and all points of entry in between,
and the final in-state or out-of-state disposition of E and P waste transmitted
through the pipeline system;
f.
detailed plans for generator, transporter and commercial facility or transfer
station operator compliance with manifesting requirements of Subsection C of
this Section and LAC 43:XIX.545.
2. The Office of Conservation shall be
notified in writing no later than five calendar days following completion of
construction of the E and P waste transfer pipeline system. Such notification
shall include the date, or anticipated date, when E and P waste transmission
operations are scheduled to begin.
3. The Office of Conservation shall be
notified in writing of any change in the principal officers, management, or
ownership of an E and P waste transfer pipeline system within 10 calendar days
of the change.
4. The Office of
Conservation shall be notified in writing within five calendar days of the
effective date of any change in the operational status of a pipeline system
including but not limited to any changes to the items listed in Paragraph 1 of
this Subsection, if and when a pipeline system, or section of the pipeline
system is shut-in or removed from service, brought back into service,
permanently removed from service and/or decommissioned.
B. Design, Operations and Maintenance Criteria
1. E and P waste transfer pipeline
systems shall be designed, constructed, operated and maintained in a manner
which is protective of public health, safety and welfare and the environment,
surface water, groundwater aquifers and underground sources of drinking
water.
C. Manifesting Requirements
1. All E and P waste transported
via an E and P waste transfer pipeline system shall be properly manifested in
accordance with LAC 43:XIX.545. E and P waste manifesting plans submitted for
compliance with the notification requirements of Subparagraph A.1.f of this
Section shall be approved by the Office of Conservation prior to
implementation.
D. Reporting Requirements
1. Any spills which
occur during the offsite transportation of E and P waste where any quantity of
E and P waste is released directly to the environmental, i.e., the spilled E
and P waste is not completely confined within a non-earthen metal, plastic,
fiberglass, concrete or other impervious containment system, shall be reported
by phone to the Office of Conservation within 24 hours of the spill and other
appropriate state and federal agencies in accordance with each agencies
applicable reporting requirements. A written report of the incident must be
submitted within five calendar days detailing the incident and methods of
corrective action. The report shall also include the identification of all
operators/generators utilizing the E and P waste transfer pipeline system at
the time of discharge.
2.
Initiation of pipeline repair and E and P waste removal/containment system
clean-up activities for any E and P waste spill remaining within a containment
system not required to be reported for compliance with Paragraph 1 of this
Subsection shall commence as soon as is practicable within 24 hours of
detection.
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4 et seq.
Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.