Current through Register Vol. 50, No. 9, September 20, 2024
A. The Office of Conservation will review a new commercial facility or transfer station application within 90 days of receipt and inform the applicant of its completeness.
B. If the application is not complete, the applicant shall be advised of additional information to be submitted for approval or the application shall be returned and the applicant will be required to resubmit the application.
C. Upon acceptance of the application as complete, the Office of Conservation shall set a time and date and secure a location for the required public hearing to be held in the affected parish.
D. The public hearing shall be fact finding in nature and not subject to the procedural requirements of the Administrative Procedure Act. All interested persons shall be allowed the opportunity to present testimony, facts, or evidence related to the application or to ask questions.
E. At least 30 days prior to the hearing, the applicant is required to file six copies of the complete application with the local governing authority of the parish in which the proposed facility is to be located to be made available for public review. Two additional copies of the complete application shall be filed in the parish library closest to the proposed facility.
F. Permit Issuance
G. The application for construction and operation of a new or additional transfer station by an existing commercial E and P Waste treatment and/or disposal facility permitted by the Office of Conservation to operate within the state of Louisiana shall be administratively approved or denied.
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4 et seq.