Section XI-6301 - Requirements (Formerly section 2707)
Universal Citation: LA Admin Code XI-6301
Current through Register Vol. 50, No. 9, September 20, 2024
A. Each operator of an underground pipeline, after having received the notification request from the regional notification center of an intent to excavate, shall supply, prior to the proposed excavation, the following information to the person responsible for the excavation:
1. The
specific location and type of all of its underground pipelines which may be
damaged as a result of the excavation or demolition. If the surface over the
buried or submerged pipeline is to be removed, supplemental offset markings may
be used. Offset markings shall be on a uniform alignment and shall clearly
indicate that the actual facility is a specific distance away.
2. Unless otherwise required by federal or
state statutes, the specific location and type of underground pipeline may, at
the operator's option, be marked to locate the pipelines. If the pipelines are
visibly marked by the operator, they shall be marked by the operator by color
coded paint, flags, or stakes or similar means using the American Public Works
Association color code.
a. When the operator
has marked the location of underground pipelines, the marking shall be deemed
good as long as visible but not longer than 20 calendar days, including
weekends and holidays, from the mark by time. An additional notice to the
regional notification center shall be given by the excavator or demolisher in
accordance with the provisions of this Chapter when the marks are no longer
visible or if the excavation or demolition cannot be completed within 20
calendar days from the mark by time, whichever occurs first.
b.
i.
Concerning locations of excavation in or on water, an excavator may request an
extension to the expiration date of a regional notification center ticket under
the following circumstances:
(a). no
utilities other than pipelines are listed on the regional notification center
ticket; and
(b). the pipeline
markings are still visible.
ii. Requests for an extension shall be made
via email to PipelineInspectors@la.gov on a form as provided by the
commissioner. The operator(s) listed on the regional notification center ticket
shall be copied on the extension request.
c. The excavator shall use all reasonable and
prudent means, within common industry practice, to protect and preserve all
marks of the underground pipeline.
3. If the pipeline(s) cannot be physically
located, the operator shall provide information to enable an excavator using
reasonable and prudent means to determine the approximate location of the
pipeline. The information provided by the operator shall include a contact
person and a specific telephone number for the excavators to call. After the
operator has received the notification request, the information on location,
size, and type of underground pipeline must be provided by the operator to the
excavator prior to excavation.
4.
In the event of inclement weather as defined in this Chapter, the mark by time
shall be extended by a duration equal to the duration of the inclement weather.
The owner or operator shall notify the excavator or demolisher before the
expiration of the mark by time of the need for such extension.
5. Should an operator determine that their
pipeline(s) is not in conflict with the location of the request or should the
pipeline(s) not be fully marked for locating purposes, a notification shall be
sent to the excavator prior to the mark by time. A response to the Regional
Notification Center that generated the locate request shall suffice for
compliance with this section.
B. For the purpose of this Section, the specific location of the underground pipeline(s) is defined as an area not wider than the width of the underground pipeline as marked plus eighteen inches on either side.
AUTHORITY NOTE: Promulgated in accordance with 40:1749.27.
Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.