A. Any pipe installed underground must have at least 12 inches of clearance between the outside of the pipe and the extremity of any other underground structure, except that for drainage tile the minimum clearance may be less than 12 inches but not less than 2 inches. However, where 12 inches of clearance is impracticable, the clearance may be reduced if adequate provisions are made for corrosion control.

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4(C)(17) and R.S. 30:1104(A).

Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.