Louisiana Administrative Code
Title 43 - NATURAL RESOURCES
Part V - Office of Mineral Resources
Chapter 9 - Leasing State Owned Lands and Water Bottoms for the Exploration, Development and Production of an Alternative Energy Source
Subchapter E - Decommissioning Requirements
Section V-966 - Process of Decommissioning Application [Formerly LAC 43:I.1166]

Universal Citation: LA Admin Code V-966

Current through Register Vol. 50, No. 9, September 20, 2024

A. Upon lessees compliance with §1165 of this Chapter, OMR or other state agencies may request a technical and environmental review based on a comparison of the decommissioning application and the decommissioning general concept in the approved COP.

B. The lessee may be required to revise the COP and begin the appropriate NEPA analysis and/or other regulatory reviews, as required, if OMR or other state agencies determine that the lessees decommissioning application would:

1. result in a significant change in the impacts previously identified and evaluated in the COP;

2. require any additional federal or state permits;

3. propose activities not previously identified and evaluated in the COP.

C. During the review process, OMR or other state agencies may request additional information if it determines that the information provided is insufficient to complete the review process.

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:124.

Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.