Louisiana Administrative Code
Title 43 - NATURAL RESOURCES
Part V - Office of Mineral Resources
Chapter 7 - Leasing State Lands and Water Bottoms for the Exploration, Development and Production of Wind Energy
Section V-729 - State Wind Lease Operations [Formerly LAC 43:I.1029]
Current through Register Vol. 51, No. 3, March 20, 2025
A. The state wind lessee and state wind lease operator shall schedule a pre-operations meeting with and submit an operations packet to the Office of Mineral Resources at least 30 days prior to commencement of construction. The operations packet shall contain the following items:
B. At the expiration of the primary term, production of wind generated electric power shall be required to maintain the lease in force. If the lessee is producing wind generated electric power, the lease shall continue in force so long as production of wind generated electric power continues without lapse of more than 180 days. Any lapse in production of wind generated electric power greater than 180 days shall result in automatic termination of the lease.
C. On or before five years after the lessee commences the production of wind generated electric power on the lease, or five years from the end of the primary term, whichever is sooner (said date being the "Undeveloped Acreage Release Date"), the lessee shall release undeveloped acreage pursuant to the requirements of this Subpart, as well as those set forth in §727
D. Any and all wind data collected during the primary term of the lease by the state wind lessee shall be released to public record at the end of the primary term.
E. The Office of Mineral Resources may require periodic reporting.
AUTHORITY NOTE: Promulgated in accordance with R.S. 41:1734.