A. Feasibility. The state shall bear 100 percent of the feasibility costs of all coastal restoration projects.
B. Design and Construction. In all cases in which the local sponsor is able to identify and secure any appropriate non-trust-fund source(s) to fund the design and/or construction of a coastal restoration project, the local sponsor share of the design and/or construction costs may consist of any form and/or amount of cost-sharing. The state share of the design and/or construction costs shall consist of any form and/or amount of cost-sharing sufficient to meet the remaining design and/or construction costs of the project for which the local sponsor is unable to cost-share.
C. Operation, Maintenance, and Monitoring
D. The state shall accept any lawful cost-sharing, as defined in §803 and shall adjust the project's cost-effectiveness ranking accordingly.
AUTHORITY NOTE: Promulgated in accordance with R.S. 49:214.4.