Section XIII-503 - Addenda Modifying Solicitations
Current through Register Vol. 50, No. 9, September 20, 2024
A. Modifications to ITB or RFP. An addendum modifying an ITB or RFP shall not be issued during the 72 hours excluding Saturdays, Sundays, and holidays preceding the response submission deadline unless the time for submitting responses is extended for at least one week.
B. Modifications to RFQ or RFQQ. An addendum modifying an RFQ or RFQQ shall not be issued during the 24 hours excluding Saturdays, Sundays, and postal holidays preceding the response submission deadline unless the time for submitting responses is extended for at least 24 hours.
C. Distribution of Addendum. Addendum(s) shall be sent to all prospective respondents known to have received a solicitation. Notification of addenda may also be made by posting on electronic bulletin boards, publication in appropriate newspapers and trade journals, email and postal notices to potential vendors, and by other means determined by the CPO.
AUTHORITY NOTE: Promulgated in accordance with R.S. 17:3139-3139.7 as amended by Act 749 of 2014.