Louisiana Administrative Code
Title 33 - ENVIRONMENTAL QUALITY
Part XV - Radiation Protection
Chapter 17 - Licensing and Radiation Safety Requirements for Irradiators
Section XV-1707 - Start of Construction
Current through Register Vol. 50, No. 9, September 20, 2024
A. An applicant for a license shall not begin construction of a new irradiator prior to the submission to the Office of Environmental Compliance of both an application for a license for the irradiator and any fee required by the applicable state requirement or statute. As used in this Chapter, the term construction includes the construction of any portion of the permanent irradiator structure on the site but does not include engineering and design work, purchase of a site, site surveys or soil testing, site preparation, site excavation, construction of warehouse or auxiliary structures, and other similar tasks. Any activities undertaken prior to the issuance of a license are entirely at the risk of the applicant and have no bearing on the issuance of a license with respect to the requirements of the appropriate state statute, rules, regulations, and orders issued under the appropriate state statute.
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:2001 et seq.