Section V-530 - Specific Part II Information Requirements for Process Vents
Current through Register Vol. 50, No. 9, September 20, 2024
Except as otherwise provided in LAC 33:V.1501, owners and operators of facilities that have process vents to which LAC 33:V. Chapter 17. Subchapter A applies must provide the following additional information.
A. Facilities that cannot install a closed-vent system and control device to comply with the provisions of LAC 33:V. Chapter 17. Subchapter A, on the effective date that the facility becomes subject to the provisions of LAC 33:V.Chapter 17.Subchapter A, and Chapter 43.Subchapter Q, must provide an implementation schedule as specified in LAC 33:V.1709.A.2.
B. Documentation of compliance with the process vent standards in LAC 33:V.1707 must be provided, including:
C. Owners or operators who apply for permission to use a control device other than a thermal vapor incinerator, catalytic vapor incinerator, flare, boiler, process heater, condenser, or carbon adsorption system to comply with the requirements of LAC 33:V.1707, and choose to use test data to determine the organic removal efficiency or the total organic compound concentration achieved by the control device must provide a performance test plan as specified in LAC 33:V.1713.B.3.
D. Documentation of compliance with LAC 33:V.1709 must be provided, including:
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:2180 et seq.