A. Written Plan. The owner or operator of a hazardous waste disposal unit must have a written post-closure plan. In addition, certain surface impoundments and waste piles from which the owner or operator intends to remove or decontaminate the hazardous wastes at partial or final closure are required by LAC 33:V.2911.D and 2315.C to have contingent post-closure plans. Owners or operators of surface impoundments and waste piles not otherwise required to prepare contingent post-closure plans under LAC 33:V.2315.C and 2911.D must submit a post-closure plan to the Office of Environmental Services within 90 days from the date that the owner or operator or administrative authority determines that the hazardous waste management unit must be closed as a landfill, subject to the requirements of LAC 33:V.3519-3527. The plan must be submitted with the permit application, in accordance with LAC 33:V.517.P, and approved by the administrative authority as part of the permit issuance procedures under these regulations. In accordance with LAC 33:V.311 the approved post-closure plan will become a condition of any hazardous waste permit issued.
B. For each hazardous waste management unit subject to the requirements of this Section, the post-closure plan must identify the activities that will be carried on after closure of each disposal unit and the frequency of these activities, and include at least:
C. Until final closure of the facility, a copy of the approved post-closure plan must be furnished to the administrative authority upon request, including request by mail. After final closure has been certified, the person or office specified in Paragraph B.3 of this Section must keep the approved post-closure plan during the remainder of the post-closure period.
D. Amendment of Plan. The owner or operator must submit to the Office of Environmental Services a written notification of or request for a permit modification to authorize a change in the approved post-closure plan in accordance with the applicable requirements of LAC 33:V.Chapters 3 and 7. The written notification or request must include a copy of the amended post-closure plan for review or approval by the administrative authority.
E. Certification of Completion of Post-Closure Care. No later than 60 days after completion of the established post-closure care period for each hazardous waste disposal unit, the owner or operator must submit to the Office of Environmental Services, by registered mail, a certification that the post-closure care period for the hazardous waste disposal unit was performed in accordance with the specifications in the approved post-closure plan. The certification must be signed by the owner or operator and an independent engineer. Documentation supporting the independent registered professional engineer's certification must be furnished to the administrative authority upon request until he releases the owner or operator from the financial assurance requirements for post-closure care under LAC 33:V.3711.I.