Section V-1735 - Standards: Closed-Vent Systems and Control Devices
Universal Citation: LA Admin Code V-1735
Current through Register Vol. 50, No. 9, September 20, 2024
A. Owners or operators of closed-vent systems and control devices subject to this Subchapter shall comply with the provisions of LAC 33:V.1709.
B.
1. The owner or operator of an existing
facility who cannot install a closed-vent system and control device to comply
with the provisions of this Subchapter on the effective date that the facility
becomes subject to the provisions of this Subchapter must prepare an
implementation schedule that includes dates by which the closed-vent system and
control device will be installed and in operation. The controls must be
installed as soon as possible, but the implementation schedule may allow up to
30 months after the effective date that the facility becomes subject to this
Subchapter for installation and start-up.
2. Any unit that begins operation after
December 21, 1990, and is subject to the provisions of this Subchapter when
operation begins, must comply with the rules immediately (i.e., must have
control devices installed and operating on start-up of the affected unit); the
30-month implementation schedule does not apply.
3. The owner or operator of any facility in
existence on the effective date of an EPA regulatory amendment that renders the
facility subject to this Subchapter shall comply with all requirements of this
Subchapter as soon as practicable, but no later than 30 months after the
regulation's effective date. When control equipment required by this Subchapter
can not be installed and begin operation by the effective date of the
amendment, the facility owner or operator shall prepare an implementation
schedule that includes the following information: specific calendar dates for
award or contracts or issuance of purchase orders for the control equipment;
initiation of on-site installation of the control equipment; completion of the
control equipment installation; and performance of any testing to demonstrate
that the installed equipment meets the applicable standards of this Subchapter.
The owner or operator shall enter the implementation schedule in the operating
record or in a permanent, readily available file located at the
facility.
4. Owners and operators
of facilities and units that become newly subject to the requirements of this
Subchapter after December 8, 1997, due to an action other than those described
in Paragraph B.3 of this Section must comply with all applicable requirements
immediately (i.e., must have control devices installed and operating on the
date the facility or unit becomes subject to this Subchapter; the 30-month
implementation schedule does not apply).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:2180 et seq.
Disclaimer: These regulations may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.