Current through Register Vol. 50, No. 9, September 20, 2024
A.
Applicability
1. This Section is applicable
to each process unit at petroleum refineries, natural gas processing plants,
synthetic organic chemical manufacturing industry (SOCMI) facilities, methyl
tertiary butyl ether (MTBE) manufacturing facilities, and polymer manufacturing
facilities that contains any of the following components that operate in
volatile organic compound (VOC) service for 300 hours or more during the
calendar year:
a. pumps;
b. compressors;
c. pressure relief devices;
d. open-ended valves or lines;
e. process drains;
f. valves;
g. agitators;
h. instrumentation systems; and
i. connectors.
2. The requirements of this Section shall be
applicable to sources located in the parishes of Ascension, East Baton Rouge,
Iberville, Livingston, Pointe Coupee, and West Baton Rouge effective January 1,
1996.
3. The requirements of this
Section shall be applicable to sources located in the parish of Calcasieu
effective January 1, 2003.
4. When
the provisions of this Section are effective, process units to which this
Section applies that are also subject to the provisions of LAC 33:III.2121 will
not be required to comply with the provisions of LAC 33:III.2121.
5. Facilities listed in Paragraph A.1 of this
Section, which are subject to new source performance standa40 CFR rds,
60.480-489 (subpart VV), 60.590-593 (subpart GGG), 60.630-636 (subpart KKK), as
incorporated by reference in LAC 33:III.3003, or national emission standards
for hazardous air pollutants, 40 CFR 61 .240-247 (subpart V), as incorporated
by reference in LAC33:III.5116, may become exempt from this Section by:
a. submitting a written notice to the
administrative authority* as
defined in LAC 33:III.111.A informing them of the facility's request to become
exempt from this Section and how 40 CFR 60 .480-489 (subpart VV), 60.590-593
(Subpart GGG), 60.630-636 (Subpart KKK), as incorporated by reference in LAC
33:III.3003, or 40 CFR 61.240-247 (subpart V), as incorporated by reference in
LAC 33:III.5116, will be administered to obtain the exemption;
b. applying 40 CFR 60.480-489 (subpart VV),
60.590-593 (subpart GGG), 60.630-636 (subpart KKK), as incorporated by
reference in LAC 33:III.3003, or 40 CFR 61.240-247 (subpart V), as incorporated
by reference in LAC 33:III.5116, to leak limitations specified in Paragraph C.1
of this Section rather than 10,000 ppm as specified in
40 CFR
60.480 - 489 (subpart VV), 60.590-593
(subpart GGG), 60.630-636 (subpart KKK), as incorporated by reference in LAC
33:III.3003, or 40 CFR 61.240-247 (subpart V), as incorporated by reference in
LAC 33:III.5116;
c. including
connectors as components monitored and repaired using the restrictions in 40
CFR 60.480-489 (subpart VV), 60.590-593 (subpart GGG), 60.630-636 (subpart
KKK), as incorporated by reference in LAC 33:III.3003, or
40 CFR
61.240 - 247 (subpart V), as incorporated by
reference in LAC 33:III.5116, which apply to valves; and
d. increasing the monitoring frequency of
valves only when the valves monitored and repaired using the restrictions in 40
CFR 60.480-489 (subpart VV), 60.590-593 (subpart GGG), 60.630-636 (subpart
KKK), as incorporated by reference in LAC 33:III.3003, or
40 CFR
61.240 - 247 (subpart V), as incorporated by
reference in LAC 33:III.5116, which apply to valves, equal or exceed 2 percent
of the valves leaking at or above 10,000 ppm.
B. Definitions. Terms used in this Section
are defined in LAC 33:III.111 with the exception of those terms specifically
defined as follows.
Alternative Work Practice (AWP)-the use
of optical imaging to detect leaks as described in
40 CFR
60.18(g), (h) and
(i).
Connector-flanged, screwed, or other
joined fittings used to connect two pipelines or a pipeline and a piece of
equipment. Joined fittings welded completely around the circumference of the
interface are not considered connectors.
Difficult-to-Monitor-equipment that
cannot be monitored without elevating the monitoring personnel more than 2
meters above a support surface.
Double Block and Bleed System-two block
valves connected in series with a bleed valve or line that can vent the line
between the two block valves.
Equipment-each pump, compressor, pressure
relief device, open-ended valve or line, process drain, valve, agitator,
instrumentation system, and connector that is in VOC service. For the purpose
of these regulations equipment shall be synonymous with
component.
Force Majeure-an event that will be or
has been caused by circumstances beyond the control of the affected facility,
its contractors, or any entity controlled by the affected facility that
prevents the owner or operator from complying with the regulatory requirement
within the specified time frame despite the affected facility's best efforts to
fulfill the obligation. Examples of such events are:
a. acts of nature;
b. acts of war or terrorism; or
c. equipment failure or safety hazard beyond
the control of the affected facility.
In Gas/Vapor Service-equipment that
contains a VOC in a gas or vapor state at operating conditions.
In Heavy Liquid Service-equipment that is
not in gas/vapor service or light liquid service.
In Light Liquid Service-
a. equipment containing a fluid that meets
all of the following conditions:
i. the vapor
pressure of one or more of the organic compounds is greater than 0.3 kPa
(0.0435 psi) at 20°C (68°F). (Standard reference texts or ASTM D2879-83, 96, or
97 shall be used to determine the vapor pressure.);
ii. the total concentration of the pure
organic compounds having a vapor pressure greater than 0.3 kPa at 20°C is equal
to or greater than 20 percent by weight; and
iii. the fluid is a liquid at operating
conditions.
b. In the
alternative to Subparagraph a of this Paragraph, an owner or operator of
petroleum refineries, natural gas processing plants, and polymer manufacturing
facilities has the option to use ASTM Method D86-78, 82, 90, 95, or 96. The
equipment is in
light liquid service if the
evaporated fluid weight is greater than 10 percent at 150°C (302°F).
In Liquid Service-equipment that is not
in gas/vapor service.
In Vacuum Service-equipment operating at
an internal pressure that is at least 20 inches of water (38 millimeters of
mercury) below ambient pressure.
In VOC Service-for petroleum refineries,
SOCMI facilities, MTBE manufacturing facilities, and polymer manufacturing
facilities; a piece of equipment that contains or contacts a process fluid that
is at least 10 percent VOC by weight. For natural gas processing plants, a
piece of equipment that contains or contacts a process fluid that is at least
1.0 percent VOC by weight.
Inspect-examine the component for
visible, audible, or olfactory evidence of a leak.
Instrumentation System-a group of
equipment components used to condition and convey a sample of the process fluid
to analyzers and instruments for the purpose of determining process operating
conditions (e.g., composition, pressure, flow). Valves and connectors are the
predominant types of equipment used in instrumentation
systems; however, other types of equipment may also be included in
these systems. Only valves nominally 0.5 inches and smaller and connectors
nominally 0.75 inches and smaller in diameter are considered
instrumentation systems for the purposes of this Section.
Valves greater than nominally 0.5 inches and connectors greater than nominally
0.75 inches associated with instrumentation systems are not
considered part of instrumentation systems and shall be
monitored individually as a valve or connector.
Monitor(ed)-determination of VOC
concentration at equipment components in accordance with method 21 (see 40 CFR
60, Appendix A-7), or the alternative work practice as
provided in this Section.
Open-Ended Valve or Line-any valve,
except pressure relief valves, having one side of the valve seat in contact
with process fluid and one side open to the atmosphere, either directly or
through open piping.
Optical Gas Imaging Instrument-an
instrument that makes emissions visible that may otherwise be invisible to the
naked eye.
Process Drain-any opening (including a
covered or controlled opening) that receives or conveys wastewater into a
wastewater system.
Process Unit-a facility, or any part
thereof, that can operate independently if supplied with sufficient feed or raw
materials and sufficient storage facilities for the product.
Process Unit Shutdown-a work practice or
operational procedure that stops production from a process unit or part of a
process unit during which it is technically feasible to clear process material
from a process unit or part of a process unit consistent with safety
constraints and during which repairs can be effected. The following are not
considered process unit shutdowns:
a. an unscheduled work practice or
operational procedure that stops production from a process unit or part of a
process unit for less than 24 hours;
b. an unscheduled work practice or
operational procedure that would stop production from a process unit or part of
a process unit for a shorter period of time than would be required to clear the
process unit or part of the process unit of materials and start-up the unit,
and would result in greater emissions than delay of repair of leaking
components until the next scheduled process unit
shutdown;
c. the use of
spare equipment and technically feasible bypassing or isolating of equipment
without stopping production; and
d.
the idling of a process unit due to force majeure.
Repair-adjust or otherwise alter
equipment in order to eliminate a leak.
Unsafe-to-Monitor-equipment that cannot
be monitored without exposing monitoring personnel to immediate
danger.
C.
Fugitive Emission Control Requirements
1.
Leak Limitations
a. No component listed in
Subparagraphs A.1.a-i of this Section in petroleum refineries, SOCMI
facilities, MTBE manufacturing facilities, and polymer manufacturing facilities
shall be allowed to emit VOC:
i. exceeding an
instrument reading of 1,000 parts per million (ppm) for valves, connectors,
instrumentation systems, pressure relief devices, and process drains; 5,000 ppm
for pumps and compressors; or 10,000 ppm for agitators, as determined by method
21 ( 40 CFR 60, Appendix A, as incorporated by reference in LAC
33:III.3003);
ii. which can be
imaged when following the alternative work practice (AWP) as
defined in Subsection B of this Section; or
iii. where visible, audible, or olfactory
evidence indicates the presence of a leak.
b. No component listed in Subparagraphs
A.1.a-i of this Section in natural gas processing plants shall be allowed to
emit VOCs exceeding an instrument reading of 2,500 ppm for valves, connectors,
instrumentation systems, pressure relief devices, and process drains; 5,000 ppm
for pumps and compressors 10,000 ppm for agitators, as determined by method 21
( 40 CFR 60, Appendix A, as incorporated by reference in LAC 33:III.3003), or
which can be imaged when following the AWP described in
40 CFR
60.18.
2. Open-Ended Valves or Lines
a. Each open-ended valve or line shall be
equipped with a second valve, a blind flange, a plug, or a cap. Such sealing
devices may be removed only when the line is in use, (i.e., when a sample is
being taken). When the line has been used and is subsequently resealed, the
upstream valve shall be closed first, followed by the sealing device.
b. When a double block and bleed system is
being used, the bleed valve or line may remain open during operations that
require venting the line between the block valves, but it shall comply with
Subparagraph C.2.a of this Section at all other times.
c. Open-ended valves or lines in emergency
system(s) (i.e., pressure relief devices) that are designed to open
automatically in the event of a process upset, are exempt from the requirements
of Subsection C.2.a of this Section.
d. Open-ended valves or lines containing
asphalt, materials that would autocatalytically polymerize or would present an
explosion, serious overpressure, or other safety hazard if sealed or equipped
with a double block and bleed system, are exempt from the requirements of
Subparagraph C.2.a of this Section.
3. Leak Repair
a. The owner or operator shall make every
reasonable effort to repair a leaking component, as described in Paragraph C.1
or Subparagraph D.3.b of this Section, within 15 calendar days of detection. A
repair is considered successful if it meets any of the following conditions:
i. a component is monitored (or remonitored)
to verify that the instrument reading is below the applicable leak definition
in Paragraph C.1 of this Section;
ii. a component that has been identified as
leaking using the AWP, either meets Clause C.3.a.i of this Section, or the
emissions are no longer visible using the AWP; or
iii. a component in liquid service that has
been identified as leaking by visual, audible, or olfactory means, including,
use of the soap bubble test for natural gas processing plants, either meets
Clause C.3.a.i of this Section, or when visual, audible, or olfactory
indications of the leak have been eliminated.
b. Equipment that cannot be repaired shall be
placed on a delay-of-repair list, unless it can be isolated or bypassed to
eliminate the leak. Repair of equipment on the delay-of-repair list shall occur
by the end of the next scheduled process unit shutdown. The
administrative authority as defined in LAC 33:III.111.A
reserves the right to take enforcement action pursuant to
R.S.
30:2025, should it be determined that the
total percentage of components on the delay-of-repair list is excessive or is
causing damage to public health or the environment.
c. Equipment placed on the delay-of-repair
list in accordance with Subparagraph C.3.b of this Section may be removed from
the list if it meets any of the following conditions:
i. the equipment is monitored or imaged, and
for two consecutive monthly periods, either the instrument readings are below
the leak limitation specified in Paragraph C.1 of this Section or there are no
visible emissions using an optical gas imaging instrument pursuant to the AWP;
or
ii. the owner or operator has
undertaken additional or extraordinary efforts to repair the leaking equipment,
and subsequent monitoring or imaging demonstrates that either the instrument
readings are below the leak limitation in Paragraph C.1 of this Section, or
there are no visible emissions using an optical gas imaging instrument pursuant
to the AWP. Extraordinary efforts are non-routine repair methods (e.g., sealant
injection, clamp installation) or utilization of a closed-vent system to
capture and control the leak by at least 90 percent.
(a). The decision to monitor equipment on the
delay-of-repair list or undertake extraordinary efforts to repair equipment
shall be made solely at the owner or operator's discretion.
D. Monitoring and Inspection Requirements.
Monitoring of components by method 21 and inspections shall be conducted
according to this Subsection. After initially complying with this Subsection,
the owner or operator may elect to comply with the appropriate alternate
monitoring schedule(s) in Subsection E of this Section. In lieu of method 21
monitoring, optical imaging may be conducted in accordance with the AWP. If the
owner or operator elects to use the AWP, the requirements for instrument
specifications, instruments checks, monitoring frequency, leak survey
procedures, recordkeeping, and reporting shall be followed as described in
40 CFR
60.18(g), (h), and (i). The
alternate monitoring schedule(s) in Subsection E of this Section are not
applicable when using the AWP.
1. Petroleum
refineries, SOCMI facilities, MTBE manufacturing facilities, and polymer
manufacturing facilities shall perform the following:
a. monitor process drains one time per
calendar year (annually).
b.
monitor the following components four times per year (quarterly):
i. compressor seals;
ii. pressure relief valves in gas/vapor
service;
iii. valves in light
liquid service and valves in gas/vapor service; and
iv. pumps in light liquid service;
c. inspect pump seals visually 52
times a year (weekly);
d. inspect
or monitor all flanged connectors in accordance with either Clause D.1.d.i or
ii of this Section;
i. inspect all flanged
connectors weekly by visual, audible, or olfactory means.
ii. monitor flanged connectors in light
liquid and gas/vapor service four times per year (quarterly) as follows:
(a). either 200 or 10 percent, whichever is
less, of the flanged connectors shall be monitored each quarterly period in
accordance with a written sampling plan;
(b). the sampling plan shall ensure that at
least 66 percent of the flanged connectors monitored each quarterly period
shall not have been previously monitored, until all flanged connectors within
the process unit have been monitored;
e. inspect instrumentation systems weekly by
visual, audible, or olfactory means. As an alternative to weekly sensory
inspections, monitor individual valves and flanged connectors of an
instrumentation system in accordance with Clauses D.1.b.iii and D.1.d.ii of
this Section, respectively;
f.
records of visual, audible, or olfactory inspections of connectors and
instrumentation systems are not required unless a leak is detected.
2. Natural gas processing plants
shall perform the following:
a. inspect pump
seals and compressor seals visually 52 times a year (weekly);
b. monitor the following components four
times a year (quarterly):
i. pumps in light
liquid service;
ii. compressor
seals;
iii. pressure relief valves
in gas/vapor service; and
iv.
valves in light liquid service and valves in gas/vapor service;
c. inspect instrumentation systems
52 times a year (weekly) by visual, audible, or olfactory means. As an
alternative to weekly sensory inspections, monitor individual valves of an
instrumentation system in accordance with Clause D.2.b.iv of this
Section;
d. records of visual,
audible, or olfactory inspections of instrumentation systems are not required
unless a leak is detected.
3. Facilities listed in Paragraphs D.1 and 2
of this Section:
a. monitor any pressure
relief valve in gas/vapor service within five calendar days after it has vented
to the atmosphere. Difficult-to-monitor pressure relief valves shall be
monitored within 15 calendar days and unsafe-to-monitor pressure relief valves
shall be monitored as soon as possible, when conditions allow the component to
be safely monitored;
b. within five
calendar days, any component listed in Subparagraphs A.1.a-i of this Section
identified as leaking by visual, audible, or olfactory means shall be:
i. repaired in accordance with Clause
C.3.a.iii of this Section;
ii.
monitored using either method 21 or the AWP; or
iii. designated as a leak pursuant to method
21 or the AWP;
c.
difficult-to-monitor components shall be monitored within 15 calendar days and
unsafe-to-monitor components shall be monitored as soon as possible, when
conditions allow the component to be safely monitored. Visual, audible, or
olfactory leaks either designated as a leak, or, confirmed to be in excess of
the applicable leak limitation in Paragraph C.1 of this Section by method 21
monitoring, shall be repaired according to Subparagraph C.3.a of this
Section;
d. difficult-to-monitor
valves shall be monitored once per calendar year;
e. unsafe-to-monitor equipment shall be
monitored as soon as possible when conditions allow the component to be
monitored safely (e.g., during a shutdown);
f. any valve that is designated for no
detectable emissions, as indicated by an instrument reading of less than 500
ppm above background, is exempt from the requirements of Clause D.1.b.iii or
D.2.b.iv of this Section if the valve:
i. has
no external actuating mechanism in contact with the process fluid (e.g.,
diaphragm valves, sealed bellows valves);
ii. is operated with emissions less than 500
ppm above background as measured by Method 21; and
iii. is monitored for compliance with Clause
D.3.e.ii of this Section initially upon designation and once per calendar year
thereafter;
g. equipment
that begins operation after the initial startup date for the process unit shall
be monitored for the first time by the end of the monitoring period in which
the process unit startup is completed, or 45 calendar days after the startup
period is completed, whichever is later. Equipment that replaces leaking
equipment shall continue with the monitoring schedule for the equipment that it
replaced;
h. monitoring to verify
repairs that were made during a process unit shutdown shall occur by the end of
the monitoring period in which the process unit startup is completed, or 45
calendar days after the startup period is completed, whichever is
later.
4. Exemptions and
inspections are not required on the following:
a. pressure relief devices, pump seals or
packing, and compressor seals or packing where leaks are vented to a process or
fuel gas system, or equipped with a closed-vent system capable of capturing and
transporting leakage to a control device;
b. pressure relief devices equipped with a
rupture disc, or other similar leak-tight pressure relief component, upstream
of the pressure relief device; provided that after each pressure release, the
rupture disc, or other similar leak-tight component is replaced as soon as
practicable; but not later than 15 calendar days;
c. equipment in vacuum service;
d. equipment at natural gas processing plants
with less than 40 million standard cubic feet per day rated capacity that do
not fractionate natural gas liquids;
e. components contacting only organic
compounds exempted under LAC 33:III.2117 or mixtures of same with
water;
f. pumps and compressors
that are sealless or have a double mechanical seal;
g. pumps designed with no external shaft
penetrating the pump housing;
h.
research and development pilot facilities and small facilities with less than
100 valves in gas/vapor or liquid service;
i. insulated or buried equipment;
j. components that have been placed on a
delay-of-repair list are exempt from further monitoring until a repair has been
attempted, except that an owner or operator may monitor components on the
delay-of-repair list in accordance with Clause C.3.c.i of this Section in order
to attempt to remove equipment from the delay-of-repair list;
k. check valves;
l. process drains that are components of
individual drain systems subject to 40 CFR 60, subpart QQQ, 40 CFR 61, subpart
FF, or 40 CFR 63, subparts G or YY; and
m. process drains at facilities subject to
LAC 33:III.2153.
5.
Alternate Monitoring Program. Any facility that already has in place a fugitive
emission monitoring program which controls emissions to a higher degree than
required under this Section shall be exempted from this Section upon submittal
of a description of the program to the administrative authority* and approval
thereof. A facility which has consolidated into an overall more stringent
program in accordance with the Louisiana Consolidated Fugitive Emissions
Program (i.e., with a source notice and agreement or a title V permit) is
exempted from having to submit a description of the program to the
administrative authority*. (The Louisiana fugitive emission program
consolidation guidelines are contained in LAC 33:III.2199.Appendix
B.)
6. Force Majeure
a. If a force majeure is about to occur,
occurs, or has occurred for which the affected owner or operator intends to
assert a claim of force majeure, the owner or operator shall notify the
administrative authority, in writing, as soon as practical following the date
the owner or operator first knew, or through due diligence should have known
that the event may cause or has caused a delay in monitoring beyond the
regulatory deadline. The notification shall occur before the monitoring
deadline unless the initial force majeure event delays the notice, and in such
cases, the notification shall occur as soon as practicable.
b. The owner or operator shall provide to the
administrative authority a written description of the force majeure event and a
rationale for attributing the delay in monitoring beyond the regulatory
deadline to the force majeure; describe the measures taken or to be taken to
minimize the delay; and identify a date by which the owner or operator proposes
to conduct the monitoring. The monitoring shall be conducted as soon as
practicable after the force majeure occurs.
c. The decision to grant an extension to the
monitoring deadline is solely within the discretion of the administrative
authority. The administrative authority shall notify the owner or operator in
writing of approval or disapproval of the request for an extension as soon as
practical.
d. Until an extension of
the monitoring deadline has been approved by the administrative authority under
Subparagraph D.6.c of this Section, the owner or operator of the affected
facility remains subject to the requirements of this Section.
E. Alternate Monitoring
Frequency . The monitoring schedule in Paragraph D.1 or 2 of this Section may
be modified as follows.
1. Alternate
Standards for Valves Subject to Subparagraph D.1.b or D.2.b of This
Section-Skip Period Leak Detection and Repair
a. An owner or operator may elect to comply
with one of the alternate work practices specified in Subparagraph E.1.b, c, or
e of this Section. However, the administrative authority shall be notified in
writing before one of the alternate work practices is implemented.
b. After two consecutive quarterly leak
detection periods with the percent of leaking valves (Equation 1) equal to or
less than 2.0, an owner or operator may begin to skip one of the quarterly leak
detection periods for valves in gas/vapor and/or light liquid
service.
c. After five consecutive
quarterly leak detection periods with the percent of leaking valves (Equation
1) equal to or less than 2.0, an owner or operator may begin to skip three of
the quarterly leak detection periods for valves in gas/vapor and/or light
liquid service.
d. If, after
implementing one of the alternate work practices in Subparagraph E.1.b or c of
this Section, the percent of leaking valves (Equation 1) increases to greater
than 2.0, or the total percent of leaking and delay-of-repair valves (Equation
2) increases to greater than 4.0, the owner or operator shall comply with the
requirements in Paragraph D.1 or 2 of this Section, but subsequently may elect
to use this Subsection when the requirements are met.
e. Existing equipment that has been monitored
under LAC 33:III.2121 for fugitives at the leak definition of 10,000 ppm can
initially elect to use this alternate standard if the unit has data documented
with the administrative authority by either January 1, 1996, or for the 12
months prior to becoming subject to this Section, that indicates the percent of
leaking valves (Equation 1) is less than or equal to a 2.0 percent leak rate at
10,000 ppm for the required time periods as specified in Subparagraph E.1.b or
c of this Section.
2.
Alternate Standards for Valves Subject to Subparagraph D.1.b or D.2.b of this
Section-Increased Monitoring Frequency. If the percent of leaking valves
(Equation 1) is greater than 2.0, or the total percent of leaking and
delay-of-repair valves (Equation 2) is greater than 4.0, then an increase in
the frequency of monitoring may be required by the administrative
authority.
3. Alternate Standards
for Flanged Connectors Subject to Clause D.1.d.ii of This Section-Skip Period
Leak Detection and Repair
a. An owner or
operator may elect to comply with the alternate work practice specified in
Subparagraph E.3.b of this Section. However, the administrative authority shall
be notified in writing before the alternate work practice is
implemented.
b. After four
consecutive quarterly leak detection periods with the percent of leaking
flanged connectors (Equation 1) equal to or less than 1.0, an owner or operator
may begin to skip three of the quarterly leak detection periods for flanged
connectors in gas/vapor and/or light liquid service.
c. If, after implementing the AWP in
Subparagraph E.3.b of this Section, the percent of leaking flanged connectors
(Equation 1) increases to greater than 1.0, or the total percent of leaking and
delay-of-repair flanged connectors (Equation 2) increases to greater than 2.0,
the owner or operator shall comply with the requirements as described in Clause
D.1.d.ii of this Section, but subsequently may elect to use this Subsection
when the requirements are met.
4. Alternate Standards for Flanged Connectors
Subject to Clause D.1.d.ii of this Section-Increased Monitoring Frequency. If
the percent of leaking flanged connectors (Equation 1) is greater than 1.0, or
the total percent of leaking and delay-of-repair flanged connectors (Equation
2) is greater than 2.0, then an increase in the frequency of monitoring may be
required by the administrative authority.
5. The percent of leaking components for
which alternate control techniques are allowed by this Subsection shall be
determined for each process unit using Equation 1 below. (Equation 1 shall be
calculated separately for each component type.)
Equation 1
%C1 =
[CL]/[CT]
* 100%
where:
%C1 = percent of leaking
components
CL = number of components found
leaking by Method 21 during the monitoring period, not including components
remonitored to verify repair or components on the delay-of-repair list at the
end of the previous monitoring period
CT = number of components monitored
by Method 21 during the monitoring period, not including components remonitored
to verify repair or components on the delay-of-repair list at the end of the
previous monitoring period
6. The total percent of leaking and
delay-of-repair components for which alternate control techniques are allowed
by this Subsection shall be determined for each process unit using Equation 2.
(Equation 2 shall be calculated separately for each component type.)
Equation 2
%CT2 =
%CT2 =
[CL+CTU]/[CT+CTU]
* 100%
where:
%CT2 = total percent of leaking
components including delay-of-repair list components
CL = number of components found
leaking by Method 21 during the monitoring period, not including components
remonitored to verify repair or components on the delay-of-repair list at the
end of the previous monitoring period
CTU = number of components on the
delay-of-repair list at the end of the previous monitoring period
CT = number of components monitored
by Method 21 during the monitoring period, not including components remonitored
to verify repair or components on the delay-of-repair list at the end of the
previous monitoring period
7. Alternate Standard for Batch Processes. As
an alternate to complying with the requirements in Subsection D of this Section
an owner or operator of a batch process in VOC service may elect to comply with
one of the following alternate work practices. The batch product-process
equipment shall be tested with a gas using the procedure specified in
Subparagraph E.7.a of this Section or with a liquid using the procedure
specified in Subparagraph E.7.b of this Section.
a. The following procedure shall be used to
pressure test batch product-process equipment using a gas (e.g., air or
nitrogen) to demonstrate compliance.
i. The
batch product-process equipment train, or section of the train, shall be
pressurized with a gas to the operating pressure of the equipment. The
equipment shall be tested at a pressure lower than the lowest pressure setting
of any relief device.
ii. Once the
test pressure is obtained, the gas source shall be shut off.
iii. The test shall continue for not less
than 15 minutes, unless it can be determined in a shorter period of time that
the allowable rate of pressure drop was exceeded. The pressure in the batch
product-process equipment shall be measured after the gas source is shut off
and at the end of the test period. The rate of change in pressure in the batch
product-process equipment shall be calculated using Equation 3.
Equation 3
P
=
(Pf -
P)
t (tf
- ti)
where:
P/t = change in pressure, psi/hr
Pf = final pressure, psi
Pi = initial pressure, psi
tf - ti =
elapsed time, hours
iv. The
pressure shall be measured using a pressure measurement device (e.g., gauge,
manometer, or equivalent) that has a precision of +-2.5 millimeters (+-0.05
psi) of mercury over the range of measured test pressures and is capable of
measuring pressures up to the lowest pressure setting of any relief
device.
v. A leak is detected if
the rate of change in pressure (Equation 3) is greater than 6.9 kPa (1 psi) per
hour or if there is visible, audible, or olfactory evidence of a
leak.
b. The following
procedure shall be used to pressure test batch product-process equipment using
a liquid to demonstrate compliance.
i. The
batch product-process equipment train, or section of the train, shall be filled
with the test liquid (e.g., water, alcohol). Once the equipment is filled, the
liquid source shall be shut off.
ii. The test shall be conducted for a period
not less than 60 minutes, unless it can be determined in a shorter period of
time that the test is a failure.
iii. Each seal in the equipment being tested
shall be inspected for indications of liquid dripping or other indications of
fluid loss. If there are any indications of liquids dripping or of fluid loss,
a leak is detected.
c.
If a leak is detected, it shall be repaired and the batch product-process
equipment shall be retested before VOCs are fed to the equipment.
d. If the batch product-process equipment
fails the retest or the second of two consecutive pressure tests, it shall be
repaired as soon as practicable, but no later than 30 calendar days after the
equipment is placed in VOC service.
F. Recordkeeping
1. When a component remains leaking after
every reasonable attempt at repair within the 15-calendar day period provided
by Subparagraph C.3.a of this Section has been exhausted, a weatherproof and
readily visible tag bearing an identification number and the date the leak was
located shall be affixed to the leaking component. After the leak has been
repaired the tag may be removed.
2.
A survey log shall be maintained by the owner or operator and shall include the
following:
a. the name of the process unit
where the leaking component is located;
b. the type of the leaking
component;
c. the stream
identification at the leak;
d. the
identification number from the tag required by Paragraph F.1 of this
Section;
e. the date the leak was
located;
f. the date maintenance
was performed;
g. the date(s) the
component was rechecked after maintenance, and the results (i.e., instrument
reading; visual, audible, or olfactory results; soap bubble test results; AWP
video);
h. a record of the monitor
calibration or AWP daily instrument check;
i. a delay-of-repair list;
j. a bypassed or isolated component list;
and
k. a record of all monitoring,
imaging, and inspection results.
3. The owner or operator shall retain the
survey log for two years after the latest date specified in Paragraph F.2 of
this Section and make the log available to the administrative authority upon
request.
4. The optional use of the
AWP shall require storing video and other records of the daily instrument check
and inspections as required in
40 CFR
60.18.
G. Reporting Requirements. The owner or
operator of the affected facility shall submit a report semiannually to the
Office of Environmental Services containing the information listed in
Paragraphs G.1-5 of this Section for each calendar quarter during the reporting
period, except for affected facilities that elect to meet the requirements of
the alternate standard for batch processes in Paragraph E.5 of this Section,
for which the report shall include the information listed in Paragraphs G.6-9
of this Section. The reports are due by the last day of the month (January and
July) following the monitoring period or by an alternate date approved by the
administrative authority. The reports shall include the following information
for each quarter of the reporting period:
1.
the number of each component type for which monitoring is required by
Subsection D or E of this Section versus the number monitored;
2. the percent of leaking components
(Equation 1) for each component type and the number of leaks detected by
visual, audible, or olfactory means for each component type;
3. the total percent of leaking and
delay-of-repair components (Equation 2) for each component type;
4. a listing of all leaks that were
identified, but not repaired, within the 15-day limit, including the following
information:
a. the name of the process unit
where the leaking component is located and the date of last unit
shutdown;
b. the type of leaking
component;
c. the stream
identification at the leak;
d. the
identification number from the tag required by Paragraph F.1 of this Section,
if the component is on the delay-of-repair list;
e. the date the leak was located;
f. the monitoring or inspection
results;
g. the date maintenance
was performed;
h. the date the leak
is expected to be repaired if the component is on the delay-of-repair list;
and
i. the reason repairs failed or
were postponed;
5. a
signed statement attesting to the fact that all requirements of this Section
have been met;
6. the batch process
equipment train identification;
7.
the number of pressure tests conducted;
8. the number of pressure tests that the
equipment train failed; and
9. a
signed statement attesting to the fact that all requirements of this Section
have been met.
AUTHORITY NOTE:
Promulgated in accordance with
R.S.
30:2054.