Current through Register Vol. 50, No. 9, September 20, 2024
A. Applications for
Land WCF funds must be submitted to the DOR through an online application
available on the Louisiana State Parks website. Applications must be submitted
by April 1 (annually). Receipt of an application initiates an extensive and
highly competitive process involving DOR preparation of the federal application
package, securing clearinghouse approval, evaluation and rating. Project
applications will be ranked by score from the open project selection process
(OPSP) and forwarded to the National Park Service for federal approval.
Assistance is available from the DOR staff for completion of the online
application at any time throughout the year.
1. Initial Evaluation. DOR staff initially
review all application submittals on the first business day following April 1
annually. Identification of all required documents is completed. Applications
with substantial missing required documentation are not eligible for further
consideration. Sponsors of projects found to have existing compliance issues
are also ineligible to apply until actions are completed to meet National Park
Service standards. Sponsors of existing active projects are also not eligible
to apply until formal federal closeout procedures by the National Park Service
are finalized upon completion of the scope of work for the active project. All
project sponsors of applications deemed ineligible are notified in writing in
regards to the eligibility to participate. Proposed project sites are visited
for initial inspection and evaluation by DOR staff.
2. Review and Preparation of Application.
Eligible applicants with complete documentation are evaluated through the OPSP
and ranked in priority order. The OPSP is developed in accordance with the most
recent publication of the Statewide Comprehensive Outdoor Recreation Plan and
approved by the National Park Service (NPS). This determination of suitability
results in a priority order of projects for consideration. Projects are
presented to the State Parks and Recreation Commission (SPARC) for review. Upon
determination of eligible federal Land WCF monies, all eligible projects are
forwarded to the NPS regional office within the limits of funding.
3. Development projects must be a single
scope of work. Initial applications for projects that require additional phases
should indicate the master plan for the entire development. Supporting
documents submitted for the first of a series of phases should indicate the
entire master development plan for the facility. To receive funding assistance
for subsequent phases of development, the active project must be completed and
a new application submitted identifying the elements that will be addressed in
the current phase. Supporting documents from the original application can be
used to minimize duplication. Approval of the initial project does not imply
guarantee of assistance in subsequent phases.
4. Subsequent phases to achieve elements of a
master plan in an existing LandWCF project are prioritized in accordance with
the open project selection process. This objective scoring system prioritizes
all applications in accordance with LandWCF regulations, which are then funded
to the full extent of available federal funds. The prioritization is validated
by the SPARC prior to submission to the National Park Service for federal
review and approval.
5. Submission.
The approved application is placed in final form and officially submitted as an
application of the state of Louisiana to the NPS Southeast Regional Office. At
this point, the application is dependent on federal action for its further
progress.
6. Recommendation. As
funds become available, priority projects are recommended in their established
order through the SPARC to the SLO. If all LandWCF monies have been obligated
at the time, the project will be held in a standby basis pending release of
additional monies. As funds do become available, the application (already
qualified) is then recommended in its turn to NPS for obligation of funds.
Applications will be recommended for obligation only in an appropriate number
to utilize efficiently those funds available at that specific time.
7. Once the desired amount of funds is
"obligated" to the subject project by NPS, a project agreement will be executed
for this purpose between the NPS and the state, and a state agreement will be
executed between the state and the local government sponsor. If found not
acceptable for some reason, the application will be rejected by NPS and
returned to the applicant, via the state, with reasons for such
rejection.
8. Termination. The
qualified application, with funds obligated to its subject project, is ready
for funding and implementation. This is the final step in the preprocessing
procedure, and the application will then be terminated in one of two ways: by
successful completion of the project or by deactivating, if for some reason the
project cannot be successfully completed. Post processing of applications for
successfully completed projects will include progress reports and billings for
work performed and accounting for funds expended. The process is concluded with
formal notification by NPS of final settlement.
AUTHORITY NOTE:
Promulgated in accordance with R.S. 56:1681-1704, R.S. 56:1801-1809 and R.S.
36:201-209.