In addition to meeting the requirements of K.A.R. 82-14-3(e), each tier 3 member shall ensure that the following requirements are met:
(a) A record of receipts for each notice of intent of excavation shall be maintained for at least two years, including an audio record, if available, of each notice of intent of excavation and a written or electronic version of the notification.
(b) A copy of the tier 3 member's record documenting the notice of intent of excavation resulting in a response from the member shall be provided to the commission or to the person giving the notice of intent of excavation, upon request.
(c) A quality control program shall be established and maintained. The program shall establish procedures for receiving and recording the notices of intent of excavation.