Section 82-14-2 - Excavator requirements
Current through Register Vol. 43, No. 52, December 26, 2024
In addition to the provisions of K.S.A. 66-1804, K.S.A. 66-1807, K.S.A. 66-1809, and K.S.A 66-1810 and amendments thereto, the following requirements shall apply to each excavator:
(a) If an excavator directly contacts a tier 2 member or a tier 3 member, the excavation scheduled start date shall be the later of the following:
(b) Unless all affected operators have provided notification to the excavator, excavation shall not begin at any excavation site before the excavation scheduled start date.
(c) If a meet on site is requested by the excavator, the excavation scheduled start date shall be no earlier than the fifth working day after the date on which the notice of intent of excavation was given to the notification center or to the tier 2 member or tier 3 member.
(d) Each notice of intent of excavation shall include the name and telephone number of the individual who will be representing the excavator.
(e) Each description of the excavation site shall include the following:
(f) If the excavation site is outside the boundaries of any city or if a street address is not available, the description of the excavation site shall include one of the following:
(g) An excavator shall not claim preengineered project status, as defined in K.S.A. 66-1802 and amendments thereto, unless the public agency responsible for the project performed the following before allowing excavation:
(h) If an excavator wishes to conduct an excavation as a permitted project, as defined in K.S.A. 66-1802 and amendments thereto, the permit obtained by the excavator shall have been issued by a federal, state, or municipal governmental entity and shall have been issued contingent on the excavator's having met the following requirements:
(i) If the excavator requests a meet on site as part of the description of the proposed excavation site given to the notification center, the tier 2 member, or the tier 3 member, then the excavator shall document the meet on site and any subsequent meetings regarding facility locations with a record noting the name and company affiliation for the representative of the excavator and the representative of the operator that attend the meeting. The excavator shall keep this record for at least two years. This documentation shall include the following:
(j) Each excavator using trenchless excavation techniques shall develop and implement operating guidelines for trenchless excavation techniques. At a minimum, the guidelines shall require the following:
(k) If any contact with or damage to any underground facility or the facility's associated tracer wire, locate ball, or associated surface equipment occurs, the excavator shall immediately inform the operator.