Kansas Administrative Regulations
Agency 5 - DEPARTMENT OF AGRICULTURE-DIVISION OF WATER RESOURCES
Article 8 - CERTIFICATION OF WATER RIGHTS
Section 5-8-4 - Construction of diversion works
Current through Register Vol. 43, No. 39, September 26, 2024
(a) A reasonable period of time for construction of diversion works shall be not less than one full year following the approval of the application to appropriate water. If a person demonstrates that a reasonable long-term schedule for development of diversion works or other infrastructure is in the public interest, that information shall be taken into consideration by the chief engineer in determining a reasonable period of time for the construction of diversion works.
(b) For good cause shown by the applicant, a reasonable extension of time to construct the diversion works shall be allowed by the chief engineer, if the request for extension is filed pursuant to the requirements of K.A.R. 5-3-7 and is accompanied by the statutorily required filing fee.
(c) If the total time allowed to construct the diversion works has been more than 16 months and fewer than 24 months, an extension of time shall be granted by the chief engineer only if the applicant meets the following criteria:
(d) If the total time allowed to construct the diversion works equals or exceeds 24 months, an extension of time may be granted only if the applicant demonstrates to the chief engineer that circumstances beyond the control of the applicant necessitate the extension of time.