Section 5-46-1 - General permits; bridge and culvert replacement projects
Current through Register Vol. 43, No. 39, September 26, 2024
(a) Except as provided in subsection (e), the construction of any bridge or culvert replacement project with a watershed of 2,560 or more acres in zone one, 3,840 or more acres in zone two, and 5,120 or more acres in zone three shall meet the criteria in subsection (c) of this regulation. Before construction, the applicant shall apply for and obtain a general permit from the chief engineer. The application shall be filed on a form prescribed by the chief engineer and shall be accompanied by plans or sketches meeting the requirements of K.A.R. 5-42-2.
(b) Except as provided in subsection (e), the construction of any bridge or culvert replacement project with a watershed of fewer than 2,560 acres in zone one, 3,840 acres in zone two, and 5,120 acres in zone three shall meet the criteria in subsection (c) of this regulation. Before construction, the applicant shall properly complete an application for, and receive the consent of, the chief engineer. The application shall be filed on a form prescribed by the chief engineer.
(c) Each bridge replacement and culvert replacement project shall meet all of the following criteria:
(d) If any bridge or culvert replacement project does not meet the requirements of this regulation, the applicant may apply for a nongeneral permit pursuant to K.S.A. 82a-301 et seq., and amendment thereto, before construction.
(e) If any bridge or culvert replacement project does not meet the requirements of this regulation or the chief engineer determines that the project may have an unreasonable effect on the public interest, public safety, or environmental interests, the right to perform the following shall be reserved by the chief engineer: