Kansas Administrative Regulations
Agency 5 - DEPARTMENT OF AGRICULTURE-DIVISION OF WATER RESOURCES
Article 40 - DESIGN OF EARTH DAMS
Section 5-40-70 - Construction notification to the chief engineer

Universal Citation: KS Admin Regs 5-40-70

Current through Register Vol. 43, No. 39, September 26, 2024

Each holder of a permit to construct, or an approval to repair or modify a dam, shall notify the chief engineer at least 48 hours before any of the following stages of construction and shall obtain the approval of the chief engineer before proceeding with each of these stages of construction:

(a) Starting construction;

(b) placing backfill in the cutoff trench;

(c) placing backfill around the primary spillway conduit or any other conduit that extends through the dam embankment and exits the downstream slope; and

(d) starting any stage of construction not specified in this regulation for which the permit requires that the chief engineer shall be notified.

Disclaimer: These regulations may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.