Kansas Administrative Regulations
Agency 5 - DEPARTMENT OF AGRICULTURE-DIVISION OF WATER RESOURCES
Article 40 - DESIGN OF EARTH DAMS
Section 5-40-105 - Procedure for independent review of an application to construct a dam or other water obstruction
Current through Register Vol. 43, No. 39, September 26, 2024
(a) When an applicant provides a copy of that individual's application to an approved reviewer pursuant to K.S.A. 82a-302 and amendments thereto, the applicant shall also submit the following to the chief engineer:
(b) The review required by the water projects environmental coordination act, K.S.A. 82a-325 et seq. and amendments thereto, shall be initiated by the chief engineer after the chief engineer receives the application.
(c) Within 37 days after the review specified in subsection (b) is initiated by the chief engineer, any comments received from the environmental review agencies shall be sent by the chief engineer to the reviewer.