Kansas Administrative Regulations
Agency 5 - DEPARTMENT OF AGRICULTURE-DIVISION OF WATER RESOURCES
Article 13 - SAND AND GRAVEL PIT OPERATIONS
Section 5-13-10 - Time to construct the diversion works for a sand and gravel pit operation

Universal Citation: KS Admin Regs 5-13-10

Current through Register Vol. 43, No. 12, March 20, 2024

(a) As used in this regulation, "completion of diversion works" means that both of the following have occurred:

(1) All equipment necessary to begin to operate a sand and gravel operation, including the hydraulic dredge, has been installed.

(2) Sufficient overburden has been excavated to begin to expose the groundwater to evaporation.

(b) A reasonable time to construct the diversion works for a sand and gravel pit operation shall be not less than one full year following the approval of the application to appropriate water.

(c) For good cause shown by the applicant, a reasonable extension of time to construct the diversion works shall be allowed by the chief engineer if both of the following conditions are met:

(1) The request for extension is filed pursuant to the requirements of K.A.R. 5-3-7.

(2) The request for extension is accompanied by the statutorily required filing fee.

Disclaimer: These regulations may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.