Kansas Administrative Regulations
Agency 36 - KANSAS DEPARTMENT OF TRANSPORTATION
Article 30 - CONSTRUCTION BIDDING PROCEDURES
Section 36-30-3 - Qualification of bidders
Current through Register Vol. 43, No. 52, December 26, 2024
(a) A prequalification committee composed of the director of operations, the bureau chief of construction and maintenance, and the controller shall determine the qualification rating for all prospective bidders, in accordance with the special provisions set forth at K.A.R. 36-30-2.
(b) Any contractor dissatisfied by the qualification rating of the committee may, within 10 days after its receipt, request in writing a reconsideration of the rating. This request shall list reasons for dissatisfaction.
(c) Any contractor who is dissatisfied with the final action taken by the committee may, within 10 days after receipt of notification of the final action, appeal to the secretary, in writing, for a final hearing.