(a) Each brine pond permittee shall submit a closure plan, including monitoring and testing requirements, to the secretary for review and consideration for approval at least 60 days before the closure of a brine pond. The closure plan shall be approved if the secretary determines that the closure plan is protective of public health, safety, and the environment.

(b) The permittee shall not commence closure activities without the secretary's prior approval.

(c) Each permittee shall include the following information in the brine pond closure plan:

(1) The procedure for deactivating the various brine lines employed at the facility;

(2) the procedures for the remediation, removal, or disposal of brine, accumulated sludge in the brine pond, contaminated soils, and contaminated groundwater;

(3) a description regarding the proposed maintenance, deactivation, conversion, or demolition of the brine pond structure; and

(4) procedures addressing the plugging of any water wells or groundwater monitoring wells associated with the brine pond.

Disclaimer: These regulations may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.