Kansas Administrative Regulations
Agency 11 - STATE CONSERVATION COMMISSION
Article 7 - NON-POINT SOURCE POLLUTION CONTROL FUND
Section 11-7-10 - Cancellation of funds

Universal Citation: KS Admin Regs 11-7-10

Current through Register Vol. 43, No. 39, September 26, 2024

(a) A status report of all active NPS contracts and each district's uncommitted balance shall be prepared by the commission on or after June 1 and shall be provided to each district.

(b) Cost-share funds uncommitted and not under contract at the close of business on June 30 shall be canceled.

(c) Cost-share funds under contract for practices on which construction has not begun by June 30 shall be canceled.

(d) Cost-share funds under contract for practices on which construction has not begun by June 30, due to inclement weather or other factors beyond the control of the applicant, shall be individually evaluated by the commission and may be encumbered and continued for one year.

(e) Cost-share funds under contract for practices on which construction has begun but has not been completed by June 30 may be encumbered and continued for one year.

(f) Encumbered contracts not completed within the year of encumbrance may be canceled by the commission.

(g) Any contract may be extended by the commission beyond previously outlined guidelines if the contract is determined by the commission to be highly significant in pollution reduction and if other factors exist that are beyond the control of the applicant.

Disclaimer: These regulations may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.