Section 11-4-10 - Notification of completion

Universal Citation: KS Admin Regs 11-4-10

Current through Register Vol. 43, No. 39, September 26, 2024

(a) The sponsor of a construction project shall notify the commission and the chief engineer when the project is completed and ready for final certification by the chief engineer. The notification of completion shall be submitted on a form supplied by the commission and shall include the following:

(1) The date of completion of the project;

(2) an itemized list of all costs of construction, engineering, surveys, geological investigations, inspections, and land acquisition; and

(3) a request for final payment of funds for the project.

(b) The sponsor of a renovation project shall notify the commission when the project is completed. The notification of completion shall be submitted on a form supplied by the commission and shall include the following information:

(1) The date of completion of the project;

(2) an itemized list of all costs of restoration, engineering, surveys, geological investigations, inspections, and land acquisition costs;

(3) a final bathymetric survey and a determination of the final excavated volume; and

(4) a request for final payment.

(c) Final disbursement of the funds due from appropriated state funds shall be made after receipt of final certification from the chief engineer.

Disclaimer: These regulations may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.