(1) Notice of eminent domain proceedings. If a petition for a franchise or amendment of franchise seeks the right of eminent domain, the electric company shall, in addition to publishing a notice of hearing, serve the written notice required by Iowa Code section 478.6(2) on the landowners and any affected person for all parcels over which eminent domain is sought. The eminent domain notice shall be filed with the commission for approval. Service shall be by certified U.S. mail, return receipt requested, and addressed to the person's last-known address. This notice shall be mailed no later than the first day of publication of the official notice of hearing concerning the petition.
(2) Notice of franchised line construction.
(3) Notice of transfer or assignment of franchise. The holder of a franchise shall notify the commission in writing, when transferring any franchise or portion of a franchise, stating the applicable franchise number and docket number which are affected and a description of the route of the transmission line when less than the total franchised line is affected, together with the name of the transferee and date of transfer, not more than 30 days after the effective date of the transfer.
(4) Notice of construction not requiring an amendment to a franchise. Whenever a transmission line under franchise is relocated or is reconstructed with different materials or specifications than those that appear on the most recent Exhibit C, or taps to a new substation or switching station are constructed along and connected to the franchised line in a manner that does not require an amendment to a franchise, the holder of the franchise shall notify the commission in writing of the construction, stating the franchise and docket numbers and date of franchise issuance for the affected transmission line, and providing revised Exhibits A, B, and C, as applicable, that reflect the changes in the route, not more than 30 days after the completion of the construction.
(5) Notice of transmission line reconstruction not requiring an amendment to franchise. Rescinded IAB 5/17/23, effective 6/21/23.