Sec. 5.

(a) The executive director may require each contractor to submit a good and sufficient bid bond with the bid. The bid bond may equal any percentage of the estimated cost of the commission works project that the executive director requires.

(b) The consulting engineer or architect may accept bids provided on forms specified by the commission or on forms provided by surety companies.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.