Sec. 9.

Each commission works contract must require that all warranty periods applying to work performed under the contract commence not later than the date that all work under the contract is substantially completed as determined by the commission.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.