Indiana Administrative Code
Title 675 - FIRE PREVENTION AND BUILDING SAFETY COMMISSION
Article 30 - INDIANA BOILER AND PRESSURE VESSEL RULES
Rule 8 - Existing Installations of Power Boilers (prior to July 1, 1953)
Section 8-9 - Fire-actuated fusible plugs

Universal Citation: 675 IN Admin Code 8-9
Current through March 20, 2024

Authority: IC 22-13-2-8

Affected: IC 22-15-6

Sec. 9.

Fire-actuated fusible plugs, if used, shall conform to the edition of the ASME B&PVC under which the power boiler in which the plugs are installed was constructed and stamped, or to the ASME B&PVC as adopted in 675 IAC 30-1-1.

Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-8-9 ) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-8-9 ) by P.L. 249-2019, SECTION 15, effective July 1, 2019.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.