Sec. 1.
(a) No boiler, except an existing installation of a boiler to be reinstalled or one exempted by 675 IAC 30-1-2, shall be installed in this state on or after July 1, 1953, unless it conforms with the edition of the ASME B&PVC in effect when the boiler was designed or constructed. A boiler installed on or after January 5, 1996 that requires an ASME B&PVC manufacturer's data report shall be registered with the NBBI.
(b) Each reinstalled or secondhand boiler shall be installed in accordance with the requirements of Part 1 of the NBIC, as referenced in 675 IAC 30-1-1.
(c) Where a boiler of special design does not comply with the adopted standards in 675 IAC 30-1-1, its construction must be approved in accordance with the variance procedure established in IC 22-13-2-11.
(d) A boiler shall not be operated until a valid operating permit is issued, as required by 675 IAC 30-39.
Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-6-1) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-6-1) by P.L. 249-2019, SECTION 15, effective July 1, 2019.