Indiana Administrative Code
Title 675 - FIRE PREVENTION AND BUILDING SAFETY COMMISSION
Article 30 - INDIANA BOILER AND PRESSURE VESSEL RULES
Rule 3 - Administration
Section 3-19 - Restamping

Universal Citation: 675 IN Admin Code 3-19
Current through September 18, 2024

Authority: IC 22-13-2-8

Affected: IC 22-15-6

Sec. 19.

When the ASME stamping on a boiler or unfired pressure vessel becomes indistinct, the inspector shall instruct the owner or user to have it restamped in accordance with the requirements in Part 2 of the NBIC. Notice of the completion of such stamping together with a facsimile of the stamping applied shall be filed with the division within thirty (30) days after the restamping is completed.

Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-3-19) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-3-19) by P.L. 249-2019, SECTION 15, effective July 1, 2019.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.