Indiana Administrative Code
Title 675 - FIRE PREVENTION AND BUILDING SAFETY COMMISSION
Article 15 - INDUSTRIALIZED BUILDING SYSTEMS
Rule 1.6 - Schedule of Fees for Industrialized Building Systems and Mobile Structures
Section 1.6-7 - Third party inspection agency authorization fees
Universal Citation: 675 IN Admin Code 1.6-7
Current through September 18, 2024
Authority: IC 22-12-6-1; IC 22-13-2-2; IC 22-13-2-13; IC 22-13-4-2
Affected: IC 22-12; IC 22-13; IC 22-15
Sec. 7.
Third party inspection authorization fees shall be as follows:
(1) Original application for Indiana third party inspection authorization | $830 |
(2) Yearly third party inspection authorization renewal | $550 |
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.