Sec. 6.
(a) The application for construction design release (ACDR) form:
(1) shall be available from the division;
and
(2) may be available from
building departments of local units of government.
(b) The ACDR shall be filed:
(1) by the owner; or
(2) on the owner's behalf by the design
professional for the project.
(c) The ACDR shall contain the following items:
(1) The:
(A) name and address of the owner;
and
(B) name, address, and
registration number of the design professional for the project, if there is
one.
(2) A description
of the land on which the proposed work is to be done by:
(A) legal description;
(B) street address; or
(C) similar description; that will readily
identify and definitely locate the proposed building or work.
(3) An identification and a
description of the work for which the application for a design release is being
made.
(4) An indication of the use
or occupancy for which the proposed work is intended.
(5) A statement of the total gross square
feet of all floors of the following:
(A) Any
Class 1 structure.
(B) Any addition
to an existing Class 1 structure.
(C) The existing portion of the Class 1
structure.
(D) Class 1 structures
that are undergoing remodeling or alteration (including both floors that are
and are not undergoing remodeling or alteration).
(6) A statement of whether or not the plans
and specifications are being submitted under
675 IAC 12-8.
(7) A statement of the estimated costs of all
construction work included in the project for which application for design
release is being made.
(8) Other
reasonable data and information concerning compliance with the rules of the
commission that the division may require.
(9) A signature by the owner or an authorized
agent certifying that the project will:
(A)
be constructed in compliance with all applicable rules of the commission;
and
(B) not be changed (unless
permitted under section 18 of this rule) from the design specified in the plans
and specifications submitted with the application and released by the division.
Any person purporting to be an agent of the owner may be required to submit written authorization of the fact.
(10) If a design professional is
required by section 9 of this rule, the application shall include a certificate
by the design professional sworn or affirmed under penalty of perjury stating
the following:
(A) That the information
required by subdivisions (1) through (8) is true and accurate.
(B) That the plans and specifications
submitted for the application:
(i) were
prepared either by or under the immediate supervision of the person making the
statement; and
(ii) provide for
construction that will meet all building laws as that term is defined by IC
22-12-1-3, including all building rules of the commission.
(C) That the construction covered by the
application will be subject to inspection at intervals appropriate to the stage
of the construction by a design professional identified in the statement for
the purpose of determining in general if work is proceeding in accordance with
the released plans and specifications.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.