Sec. 2.
(a) The
definitions in this section apply throughout this rule.
(b) "Class 1 structure" means the following:
(1) Any part of the following:
(A) A building or structure that is intended
to be or is occupied or otherwise used in any part by any of the following:
(i) The public.
(ii) Three (3) or more tenants.
(iii) One (1) or more persons who act as the
employees of another.
(B) A site improvement affecting access by
persons with physical disabilities to a building or structure described in this
subdivision.
(C) Storage
facilities, tanks, and dispensing equipment for flammable and combustible
liquids or gases.
(2)
Subdivision (1) includes a structure that contains three (3) or more
condominium units (as defined in IC 32-25-2-9) or other units that are as
follows:
(A) Intended to be or are used or
leased by the owner of the units.
(B) Not completely separated from each other
by an unimproved space.
(3) Subdivision (1) does not include the
following:
(A) A building or structure that is
as follows:
(i) Intended to be or is used only
for an agricultural purpose on the land where it is located.
(ii) Not used for retail trade or is a stand
used for retail sales of farm produce for eight (8) or fewer consecutive months
in a calendar year.
(B)
A Class 2 structure as defined by IC 22-12-1-5. One and two family dwellings
used for seasonal accommodation, including those sometimes known as "tourist
cabins" are Class 2 structures and are regulated under 675 IAC 14. (C) A
vehicular bridge.
(D) A structure
that is intended to be or is occupied solely to provide periodic maintenance or
repair of either of the following:
(i) The
structure.
(ii) Mechanical or
electrical equipment located within and affixed to the structure.
(c)
"Construction" means any of the following:
(1) Fabrication of any part of an
industrialized building system or mobile structure for use at another
site.
(2) Erection or assembly of
any part of a Class 1 or Class 2 structure at the site where it will be
used.
(3) Installation of any part
of the permanent heating, ventilating, air conditioning, electrical, plumbing,
sanitary, emergency detection, emergency communication, or fire or explosion
suppression systems for a Class 1 or Class 2 structure at the site where it
will be used.
(4) Work undertaken
to alter, remodel, rehabilitate, or add to any part of a Class 1 or Class 2
structure.
(5) Work undertaken to
relocate any part of a Class 1 or Class 2 structure, except a mobile
structure.
(d) "Design
professional" means a registered architect or professional engineer who is
registered under IC 25-4 or IC 25-31.
(e) "Structural safety" means the continued
capability of either of the following:
(1)
Load-bearing members of a building or structure to transmit actual and design
live and dead loads to a foundation.
(2) Other load-bearing members within the
allowable working stresses of the materials or assembly of materials
involved.
(f) "Temporary
structure" means any of the following:
(1) A
Class 1 structure that is erected or installed for a period of not more than
ninety (90) days after which it will be demolished or relocated.
(2) Portable structures on construction job
sites for use by persons involved in the construction process.
(3) Mobile structures as set forth at IC
22-12-1-17.
This version of section effective December 1, 2014. See
also preceding version of section, effective until December 1,
2014.