Indiana Administrative Code
Title 675 - FIRE PREVENTION AND BUILDING SAFETY COMMISSION
Article 12 - ADMINISTRATION
Rule 5 - Variances
Section 5-6.2 - Determinations
Current through September 18, 2024
Authority: IC 22-13-2-13
Affected: IC 22-12-7-3; IC 22-13-2-11; IC 22-13-2-14.1
Sec. 6.2.
(a) The department or the commission (whichever body is making the determination) shall wait at least five (5) business days following posting of a completed variance application to the public portal and payment of the variance application fee before making a determination on a variance request.
(b) The department or the commission (whichever body is making the determination) may grant a variance if the applicant:
(c) The department or the commission (whichever body is making the determination) may impose conditions on the variance other than those suggested by the applicant.
(d) An order granting or denying a variance shall be issued as required by IC 22-12-7-3.
(e) All determinations on a variance request from a rule contained in 675 IAC 30 may only be made following consultation with an industry expert as defined in IC 22-13-2-14.1.
(f) The department shall submit a report to the commission of all variance determinations made by the department since the commission's last meeting.