Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 3.1 - HAZARDOUS WASTE MANAGEMENT PERMIT PROGRAM AND RELATED HAZARDOUS WASTE MANAGEMENT
Rule 15 - Financial Requirements for Final (State) Permitted Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
Section 15-3 - Cost estimate for closure
Current through September 18, 2024
Authority: IC 13-14-8; IC 13-22-2-4
Affected: IC 13-22-2; 40 CFR 264.142
Sec. 3.
(a) The owner or operator shall keep at the facility a detailed written estimate, in current dollars, of the cost of closing the facility in accordance with the requirements in 40 CFR 264.111 through 40 CFR 264.115 and applicable closure requirements in 40 CFR 264.178, 40 CFR 264.197, 40 CFR 264.228, 40 CFR 264.258, 40 CFR 264.280, 40 CFR 264.310, 40 CFR 264.351, 40 CFR 264.601 through 40 CFR 264.603, and 40 CFR 264.1102 as follows:
(b) During the active life of the facility, the owner or operator must adjust the closure cost estimate for inflation within sixty (60) days prior to the anniversary date of the establishment of the financial instrument used to comply with section 4 of this rule. For owners and operators using the financial test or guarantee, the closure cost estimate must be updated for inflation within thirty (30) days after the close of the firm's fiscal year and before submission of updated information to the commissioner as specified in section 4(g)(3) of this rule. The adjustment may be made by recalculating the maximum costs of closure in current dollars, or by using an inflation factor derived from the most recent implicit price deflator for gross national product published by the U.S. Department of Commerce in its Survey of Current Business, as follows:
(c) During the active life of the facility, the owner or operator shall revise the closure cost estimate no later than thirty (30) days after the commissioner has approved the request to modify the closure plan if the change in the closure plan increases the cost of closure. The revised closure cost estimate must be adjusted for inflation as specified in subsection (b).
(d) The owner or operator shall keep the following at the facility during the operating life of the facility: