Authority: IC 13-14-8; IC 13-22-2; IC 13-22-8-1; IC 13-22-9-7

Affected: IC 13-22

Sec. 31.

A letter from the chief financial officer, as specified in section 9 or 19 of this rule, 329 IAC 3.1-15-4(g), or 329 IAC 3.1-15-6(g), 329 IAC 3.1-15-10(f)), must be worded as follows except that instructions in brackets are to be replaced with the relevant information and the brackets deleted:

Letter from Chief Financial Officer

[Address to commissioner of the Indiana Department of Environmental Management]

I am the chief financial officer of [name and address of firm]. This letter is in support of this firm's use of the financial test to demonstrate financial assurance, in accordance with 329 IAC 3.1-14 or 329 IAC 3.1-15.

[Complete the following four (4) paragraphs regarding facilities and associated cost estimates. If your firm has no facilities that belong in a particular paragraph, write "None" in the space indicated. For each facility, include its U.S. EPA identification number, name, address, and current corrective action, closure, and/or post-closure cost estimates. Identify each cost estimate as to whether it is for corrective action, closure, or post-closure care.]

1. This firm is the owner or operator of the following facilities for which financial assurance for corrective action, closure, or post-closure care is demonstrated through the financial test specified in 329 IAC 3.1-14 or 329 IAC 3.1-15. The current corrective action, closure and/or post-closure cost estimates covered by the financial test are shown for each facility: ______________.

2. This firm guarantees, through the guarantee specified in 329 IAC 3.1-14 or 329 IAC 3.1-15, the corrective action, closure, or post-closure care of the following facilities owned or operated by the guaranteed party. The current cost estimates for the corrective action, closure, or post-closure care so guaranteed are shown for each facility: _____________. The firm identified above is [insert either or both, as applicable: "the direct or higher tier parent corporation of the owner or operator" or "owned by the same parent corporation as the parent corporation of the owner or operator and receiving the following value in consideration of this guarantee _____________."].

3. In states other than Indiana, this firm, as owner or operator or guarantor, is demonstrating financial assurance for the corrective action, closure, or post-closure care of the following facilities either to the United States Environmental Protection Agency (U.S. EPA) or to an authorized state through the use of a financial test 329 IAC 3.1-14 or 329 IAC 3.1-15. at least equivalent to 40 CFR 264 Subpart H or 40 CFR 265 Subpart H. The current corrective action, closure, and/or post-closure cost estimates covered by such a financial test are shown for each facility: ____________.

4. This firm is the owner or operator of the following hazardous waste management facilities for which financial assurance for corrective action, closure, or, if a disposal facility, post-closure care is not demonstrated either to the U.S. EPA or a state through the financial test or any other financial assurance mechanism specified in 40 CFR 264 Subpart H and 40 CFR 265 Subpart H, or equivalent or substantially equivalent state mechanisms. The current corrective action, closure, and/or post-closure cost estimates not covered by such financial assurance are shown for each facility: ______________.

This firm [insert "is required" or "is not required"] to file a Form 10K with the Securities and Exchange Commission (SEC) for the latest fiscal year.

The fiscal year of this firm ends on [month, day]. The figures for the following items marked with an asterisk (*) are derived from this firm's independently audited, year-end financial statements for the latest completed fiscal year, ended [date].

[Fill in Alternative I if the criteria of 329 IAC 3.1-15-4(g)(1)(A), 329 IAC 3.1-15-6(g)(1)(A), 329 IAC 3.1-14-9(a)(1), or 329 IAC 3.1-14-19(a)(1) are used. Fill in Alternative II if the criteria of 329 IAC 3.1-15-4(g)(1)(B), 329 IAC 3.1-15-6(g)(1)(B), 329 IAC 3.1-14-9(a)(2), or 329 IAC 3.1-14-19(a)(2) are used.]

Alternative I

1. Sum of current corrective action, closure, and post-closure cost estimates [total of all cost $_____ estimates shown in the four paragraphs above].

* 2. Total liabilities [if any portion of the corrective action, closure, or post-closure cost estimates is $_____ included in total liabilities, you may deduct the amount of that portion from this line and add that amount to lines 3 and 4].

* 3. Tangible net worth. $_____

* 4. Net worth. $_____

* 5. Current assets. $_____

* 6. Current liabilities. $_____

7. Net working capital [line 5 minus line 6]. $_____

* 8. The sum of net income plus depreciation, depletion, and amortization. $_____

* 9. Total assets in U.S. (required only if less than 90% of firm's assets are located in the U.S.). $_____

YES NO

10. Is line 3 at least $10 million?

11. Is line 3 at least 6 times line 1?

12. Is line 7 at least 6 times line 1?

* 13. Are at least 90% of firm's assets located in the U.S.? If not, complete line 14.

14. Is line 9 at least 6 times line 1?

15. Is line 2 divided by line 4 less than 2.0?

16. Is line 8 divided by line 2 greater than 0.1?

17. Is line 5 divided by line 6 greater than 1.5?

Alternative II

1. Sum of current corrective action, closure, and post-closure cost estimates [total of all cost $_____ estimates shown in the four paragraphs above].

2. Current bond rating of most recent issuance of this firm and name of rating service.

3. Date of issuance of bond.

4. Date of maturity of bond.

* 5. Tangible net worth (if any portion of the corrective action, closure, and post-closure cost estimates is included in "total liabilities" on your firm's financial statements, you may add the amount of that portion to this line). $_____

* 6. Total assets in U.S. (required only if less than 90% of firm's assets are located in the U.S.). $_____

YES NO

7. Is line 5 at least $10 million?

8. Is line 5 at least 6 times line 1?

* 9. Are at least 90% of firm's assets located in the U.S.? If not, complete line 10.

10. Is line 6 at least 6 times line 1?

I hereby certify that the wording of this letter is identical to the wording specified in 329 IAC 3.1-14-31 as such rule was constituted on the date shown immediately below.

[Signature]

[Name]

[Title]

[Date]

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.