Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 3.1 - HAZARDOUS WASTE MANAGEMENT PERMIT PROGRAM AND RELATED HAZARDOUS WASTE MANAGEMENT
Rule 14 - Financial Requirements for Owners and Operators of Interim Status Hazardous Waste Treatment, Storage, and Disposal Facilities
Section 14-3 - Cost estimate for closure
Current through September 18, 2024
Authority: IC 13-14-8; IC 13-22-2-4
Affected: IC 13-22-2
Sec. 3.
(a) The owner or operator shall keep at the facility a detailed written estimate, in current dollars, of the cost of closing the facility in accordance with the requirements in 40 CFR 265.111 through 40 CFR 265.115, applicable closure requirements of 40 CFR 265.178, 40 CFR 265.197, 40 CFR 265.228, 40 CFR 265.258, 40 CFR 265.280, 40 CFR 265.310, 40 CFR 265.351, 40 CFR 265.381, 40 CFR 265.404, and 40 CFR 265.1102, and the following:
(b) During the active life of the facility, the owner or operator shall adjust the closure cost estimate for inflation within sixty (60) days prior to the anniversary date of the establishment of the financial instrument used to comply with section 4 of this rule. For owners and operators using the financial test or guarantee, the closure cost estimate must be updated for inflation within thirty (30) days after the close of the firm's fiscal year and before the submission of updated information to the commissioner as specified in section 9(c) of this rule. The adjustment may be made by recalculating the closure cost estimate in current dollars, or by using an inflation factor derived from the most recent implicit price deflator for gross national product published by the U.S. Department of Commerce in its Survey of Current Business, specified as follows:
The inflation factor is the result of dividing the latest published annual deflator by the deflator for the previous year.
(c) During the active life of the facility, the owner or operator must revise the closure cost estimate no later than thirty (30) days after a revision has been made to the closure plan which increases the cost of closure. If the owner or operator has an approved closure plan, the closure cost estimate must be revised no later than thirty (30) days after the commissioner has approved the request to modify the closure plan, if the change in the closure plan increases the cost of closure. The revised closure cost estimate must be adjusted for inflation as specified in subsection (b).
(d) The owner or operator must keep the following at the facility during the operating life of the facility: