Sec. 4.
(a) Renewal applications must be submitted at least one hundred twenty (120) days prior to the expiration date of the permit.
(b) A complete application for a solid waste processing facility permit renewal must consist of the following information, submitted on forms provided by the commissioner:
(c) Fees must be submitted with the application in accordance with IC 13-20-21.
(d) If the solid waste processing facility is not constructed before the permit must be renewed, the renewal application must include any construction and operation requirements as specified in this article, as amended in 2010, and applicable to the facility.