Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 11 - SOLID WASTE PROCESSING FACILITIES
Rule 2 - Definitions
Section 2-21.1 - "Major modification of solid waste processing facilities" defined

Universal Citation: 329 IN Admin Code 2-21.1

Current through March 20, 2024

Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1

Affected: IC 13-30-2; IC 36-9-30

Sec. 21.1.

"Major modification of solid waste processing facilities" means any of the following:

(1) Any increase in a permitted solid waste processing facility that would increase the facility's permitted capacity to process solid waste by more than ten percent (10%) or the addition of a major piece of equipment, such as a compactor, that increases the facility's permitted capacity to process solid waste by more than ten percent (10%).

(2) New bay loading area.

(3) New loading tunnel.

(4) Expansion of an existing loading bay or tunnel so that additional transfer trailers can be loaded simultaneously.

(5) Expansion of the existing waste processing area by more than fifty percent (50%) either through:

(A) expansion of the area within an existing building; or

(B) the addition of a new building.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.