Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 11 - SOLID WASTE PROCESSING FACILITIES
Rule 13.5 - Solid Waste Processing Facilities; Operational Requirements
Section 13.5-8 - Use of contingency action plan
Universal Citation: 329 IN Admin Code 13.5-8
Current through September 18, 2024
Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 8.
If the facility is unable to operate or process solid waste in accordance with its approved operating plan for more than a continuous twenty-four (24) hour period, the contingency action plan required in 329 IAC 11-9-2(j)(6) must be implemented.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.