Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 10 - SOLID WASTE LAND DISPOSAL FACILITIES
Rule 32 - Restricted Waste Site Type III and Construction/Demolition Sites; Additional Application Requirements to 329 IAC 10-11
Section 32-2 - Plot plans and cross-sectional drawings
Current through September 18, 2024
Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 2.
(a) An application for a restricted waste site Type III or a construction/demolition site must be accompanied by plot plans using a scale of at least one (1) inch equals one hundred (100) feet for a site of less than eighty (80) acres, or a scale of at least one (1) inch equals two hundred (200) feet for a facility of eighty (80) acres or more. A bar scale must be shown on plans in order to properly indicate the scale if size changes occur. All plot plans must include the facility boundaries and indicate each of the required features set forth in this section within three hundred (300) feet of the facility boundaries. All facility plan elevations must correlate with United States Geological Survey (USGS) mean sea level data.
(b) An application for restricted waste site Type III must be accompanied by the following plot plans and cross sections:
(c) An application for a construction/demolition site must be accompanied by the following plot plans and cross sections: