Sec. 8.
(a) The owner, operator, or permittee may develop a verification resampling and analysis plan that will provide verification that a preliminary exceedance has occurred in the concentration of one or more constituents during detection or assessment monitoring programs. This plan must:
(b) Until the owner, operator, or permittee obtains approval for a proposed verification resampling and analysis plan, a minimum of two (2) independent samples must be collected when verification of a statistically significant increase is attempted.
(c) Until the owner, operator, or permittee obtains approval for a verification resampling plan, the commissioner shall consider a preliminary exceedance to be verified if:
(d) Within fourteen (14) days following the verification resampling determination, the owner, operator, or permittee shall notify the commissioner of the following:
(e) The detection ground water monitoring program or the assessment ground water monitoring program shall continue throughout the verification resampling program. Progression to an assessment or corrective action ground water monitoring program shall be based on the verification resampling results, regardless of subsequent detection monitoring results if the verification resampling program extends into the next scheduled sampling event.
(f) Following the completion of a verification resampling program, a report must be submitted to the commissioner no later than sixty (60) days following the last verification resampling event or thirty (30) days prior to the next scheduled semiannual sampling event, whichever occurs first. This report must be written and include the following:
(g) If verification sampling determines that a statistically significant increase did occur, the owner, operator, or permittee:
(h) The commissioner may approve an extension of the submittal deadlines required by subsection (f) if the owner, operator, or permittee: