Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 10 - SOLID WASTE LAND DISPOSAL FACILITIES
Rule 17 - Municipal Solid Waste Landfill Liner System; Design, Construction, and CQA/CQC Requirements
Section 17-7 - Geomembrane component of the liner; construction and quality assurance/quality control requirements
Universal Citation: 329 IN Admin Code 17-7
Current through September 18, 2024
Authority: IC 13-14-8-7; IC 13-15; IC 13-19-3
Affected: IC 13-20; IC 36-9-30
Sec. 7.
(a) Before geomembrane field construction, the project engineer shall review documentation of quality control testing as follows:
(1) In
a review of the testing of raw materials used to manufacture the geomembrane,
the project engineer shall do the following:
(A) Ensure that the quality control testing
meets the specifications of the approved construction plan.
(B) Review copies of the origin and
identification of the raw materials.
(C) Review copies of quality control
certificates issued by the producers of the raw materials. The certificates
must be accompanied by results of the following tests unless a particular test
requirement is waived by the commissioner based on particular site or facility
conditions:
(i) Density test.
(ii) Melt flow index test.
(iii) Any other test deemed necessary by the
commissioner to verify raw material quality.
(2) In a review of the testing documentation
of the geomembrane rolls that are fabricated into geomembrane, the project
engineer shall do the following:
(A) Check the
manufacturer's certified quality control documentation to verify that the
geomembrane was continuously inspected during the manufacturing process for the
following:
(i) Lack of uniformity.
(ii) Damage.
(iii) Imperfections.
(iv) Holes.
(v) Cracks.
(vi) Thin spots.
(vii) Foreign materials.
(B) Ensure that any imperfections discovered
during inspection were repaired and then reinspected, either at the
manufacturing facility or on-site at the MSWLF.
(C) Review the results of manufacturer's
quality control tests for conformance with project specifications. These tests
must include, at a minimum, the following:
(i)
Stress crack resistance test.
(ii)
Tensile strength test.
(iii) Tear
and puncture resistance test.
(iv)
Oxidative induction time (OIT) at:
(AA)
standard OIT; or
(BB) high
pressure OIT.
(v)
Ultraviolet resistance at high pressure OIT.
(vi) Any other test deemed necessary by the
commissioner to verify quality. (3) The project engineer shall ensure that
manufacturer quality control testing of the raw materials and of the finished
geomembrane product was conducted:
(A) as
required in the approved construction plans; or
(B) as otherwise required by the commissioner
based on particular site or facility conditions.
(b) During geomembrane field construction, the project engineer shall ensure the following:
(1) The geomembrane is installed on
supporting soil that is reasonably free of the following:
(A) Stones.
(B) Organic material, except that organic
material naturally occurring in the soil.
(C) Irregularities.
(D) Protrusions.
(E) Loose soil or soft spots.
(F) Standing water.
(G) Any abrupt change in grade that could
damage the geomembrane.
(2) All aspects of geomembrane installation
are carried out in accordance with the following:
(A) The approved construction plan.
(B) The manufacturer's
recommendations.
(C) The design
standards described under section 6 of this rule.
(D) Any additional requirements necessary to
obtain adequate geomembrane liner construction and installation, as specified
in the construction plans or as determined by the commissioner to assure the
quality of the geomembrane liner.
(3) The anchor trench is excavated to the
length and width prescribed in the approved construction plans.
(4) Field seaming is conducted as follows:
(A) To meet the requirements for design of
the geomembrane component of the liner as described under section 6 of this
rule.
(B) In a manner that leaves
seams free of the following:
(i)
Dust.
(ii) Dirt.
(iii) Moisture.
(iv) Debris.
(v) Foreign material of any kind.
(C) Using an appropriate method
consistent with:
(i) the approved construction
plan; or
(ii) a method otherwise
approved by the commissioner based on equivalent environmental
protection.
(D) At a
time when the following conditions exist, unless otherwise approved by the
commissioner based on particular site or facility conditions, or project
engineer, or otherwise recommended by the manufacturer:
(i) Air temperature is at least thirty-two
(32) degrees Fahrenheit but does not exceed one hundred twenty (120) degrees
Fahrenheit.
(ii) Sheet temperature
is at least thirty-two (32) degrees Fahrenheit but does not exceed one hundred
fifty-eight (158) degrees Fahrenheit.
(iii) Wind gusts are not in excess of twenty
(20) miles per hour.
(5) Quality assurance and quality control
testing conducted in the field conforms with requirements of the approved
construction plan and includes the following:
(A) A sample is taken from each lot number of
geomembrane material that arrives on site and is tested in the following manner
for the purpose of fingerprinting the material:
(i) Thickness of the sample must be measured
at a rate of five (5) measurements per roll of geomembrane, at locations evenly
distributed throughout the roll.
(ii) The following tests must be conducted at
a rate of either once per lot or once per fifty thousand (50,000) square feet
of geomembrane:
(AA) Tensile characteristics
test for strength and elongation at yield and at break.
(BB) Carbon black content test.
(CC) Carbon black dispersion test, if
applicable.
(DD) Any additional
tests that are necessary as determined by the commissioner to demonstrate the
integrity of the geomembrane.
(B) Visual inspections of the geomembrane
material, followed by appropriate repairs and reinspections, are made for:
(i) lack of uniformity;
(ii) damage;
(iii) imperfections;
(iv) tears;
(v) punctures;
(vi) blisters; and
(vii) excessive folding.
(C) Test seams for shear strength and peel
strength are made as follows:
(i) At the start
of each work period for each seaming crew.
(ii) After every four (4) hours of continuous
seaming.
(iii) Every time seaming
equipment is changed.
(iv) When
significant changes in geomembrane temperature, as determined by the project
engineer or by manufacturer recommendation, are observed.
(v) As required in the approved construction
plan.
(vi) As may be required by
the commissioner.
(D)
Nondestructive seam testing proceeds as follows:
(i) Testing is performed on all seams over
their full length using a test method:
(AA) in
accordance with the approved construction plans;
(BB) in accordance with section 17 of this
rule; or
(CC) otherwise acceptable
to the commissioner as an equivalent test method.
(ii) Testing is monitored by the project
engineer, and seaming and patching operations are inspected for uniformity and
completeness.
(iii) Results of
testing are recorded by the project engineer in records that include the
following information:
(AA) The location of
the seam test.
(BB) The test unit
number.
(CC) The name of the person
conducting the test.
(DD) The
results of all tests.
(EE) Any
other information that may be necessary to judge the adequacy of the seaming
and patching procedures.
(E)
Geomembrane seams that cannot be nondestructively tested are overlain with
geomembrane material of identical type.
(F) Destructive seam testing is performed at
the site, or at an independent laboratory, according to the approved
construction plans, and meets the following requirements:
(i) Testing is performed:
(AA) on a minimum of one (1) test per five
hundred (500) feet of seam length if the seam is welded with a fusion weld;
and
(BB) on a minimum of one (1)
test per four hundred (400) feet of seam length if the seam is welded with an
extrusion weld; and
(CC) on a
minimum of one (1) test for each seaming machine; or
(DD) as otherwise required by the
commissioner based on a testing frequency that will result in equivalent
environmental protection.
(ii) Destructive seam testing includes:
(AA) a shear strength test; and
(BB) a peel strength test.
(iii) If a seam location fails
destructive testing:
(AA) the seam is
reconstructed over a minimum of ten (10) feet in each direction from the site
of the failed test;
(BB) additional
samples are taken for testing; and
(CC) reconstruction and retesting is
repeated, as necessary, until at least eighty percent (80%) of the samples at
the test location pass the destructive seam test.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.