Indiana Administrative Code
Title 329 - SOLID WASTE MANAGEMENT DIVISION
Article 10 - SOLID WASTE LAND DISPOSAL FACILITIES
Rule 17 - Municipal Solid Waste Landfill Liner System; Design, Construction, and CQA/CQC Requirements
Section 17-4 - Soil component of the liner; design requirements

Universal Citation: 329 IN Admin Code 17-4

Current through September 18, 2024

Authority: IC 13-14-8-7; IC 13-15; IC 13-19-3

Affected: IC 13-18; IC 13-20; IC 36-9-30

Sec. 4.

The soil components of the liner systems described in section 2 of this rule must meet the following requirements:

(1) Be constructed on a slope of no less than two percent (2%) toward the leachate collection pipes.

(2) Meet the specified thickness and hydraulic conductivity requirements of section 2 of this rule, as appropriate to the location of the proposed MSWLF unit.

(3) Be composed of lifts, each having a maximum thickness that:

(A) is specified in the approved construction plan or is otherwise approved by the commissioner; and

(B) in no case exceeds nine (9) inches after compaction.

(4) Have a design that adequately addresses the following factors:

(A) Protection from damage due to uplift from hydrostatic forces.

(B) Prevention of damage due to freeze/thaw and wet/dry cycles.

(C) Any additional factors that are necessary to obtain an adequate soil component as specified in the construction plans or as determined by the commissioner.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.